=== Past 24 hours ===
 
=== Past 24 hours ===
* No beam for
+
* No beam from 10 am to xx
  
 
=== Shift Reports ===
 
=== Shift Reports ===

Revision as of 21:18, 8 February 2023

Zoom connect Meeting ID: 160 199 0060 / Passcode 8394

MCC whiteboard

Hall D counting room white board

Spreadsheet with list of runs

Integrated Trigger Count


Wednesday February 9

Past 24 hours

  • No beam from 10 am to xx

Shift Reports

Reports

  • Statistics balance
    • PARA 0/90: 19%
    • PERP 0/90: 19%
    • PARA 45/135: 21%
    • PERP 45/135: 18%
    • AMO : 24%

Issues

Pending:

  • Start Counter (Beni) - We do not understand why there is a mismatch in the software between start counter and tracking.
  • BCM calibration. Alexandre recommends that we request a recalibration of AD00C BCM.

Plans

  • Production (300 nA, 2h runs) with cycle:
    • 2 runs PARA (0/90)
    • 2 runs PERP (0/90)
    • 2 runs PARA (45/135)
    • 2 runs PERP (45/135)
    • 1 run AMO (use it to rejuvenate AMO reference in CBREM EPICS GUI)