(Friday, April 20 at 08:45)
(Friday, April 20 at 08:45)
Line 11: Line 11:
 
#* Production running
 
#* Production running
 
# Reports:
 
# Reports:
[https://logbooks.jlab.org/entry/3563791 high current hit multiplicity in TAGM]
+
#* [https://logbooks.jlab.org/entry/3563791 high current hit multiplicity in TAGM]
 
# Issues
 
# Issues
 
#* [https://logbooks.jlab.org/entry/3563798 Issues with BCAL timing?] (Elton)
 
#* [https://logbooks.jlab.org/entry/3563798 Issues with BCAL timing?] (Elton)

Revision as of 08:47, 20 April 2018

<- Back to Run Coordination Meetings:Fall2017 Spring2018 Run

Friday, April 20 at 08:45

  1. Notes from the previous 24 hours:
  2. Reports:
  3. Issues
  4. Run Plan
    • High rate tests this afternoon
    • Production running
    • Fast raster scan deferred until Monday (probably, will hear from PD)
    • Longer term run plan
  5. AOB

Thursday, April 19 at 08:45

  1. Notes from the previous 24 hours:
  2. Issues:
  3. Reports:
  4. Run Plan
    • Access today to
      • Move active collimator to 5 mm hole
      • Attach Pb radiator to profiler
      • Muon chamber inspection
    • Production running
      • Harp scan when beam comes back
    • Fast raster scan deferred until the required people can be found
    • Future studies
  5. AOB