(October 02, 2015)
Line 85: Line 85:
 
**FFB commissioning will be concluded by low current (5nA) nA-BPM commissioning.
 
**FFB commissioning will be concluded by low current (5nA) nA-BPM commissioning.
 
**Beam line FOPT. About 2h of data. Data for beam energy stability study will be gathered at the same time.
 
**Beam line FOPT. About 2h of data. Data for beam energy stability study will be gathered at the same time.
**Tagger detector commissioning (parasitic to FFB work). Alex. B. and Richard J. provided a [https://halldweb.jlab.org/wiki/images/d/da/TAGMFall2015RunPlan.pdf test plan].
+
**Tagger detector commissioning (parasitic to FFB work). Alex. B. and Richard J. provided a [http://argus.phys.uregina.ca/gluex/DocDB/0028/002819/001/TAGMFall2015RunPlan.pdf test plan].
 
**Trigger tests
 
**Trigger tests
 
**DAQ work. The goal is to optimize DAQ performance and find DAQ rate bottlenecks: data rate, trigger rate, live time. Several parameters have to be defined for every DAQ components independently: detectors readout (for FDC,CDC,FCAL,BCAL,...), event builder, data concentrators, event recorder, to find the slowest. Optimization includes different triggers and beam current. FDC/CDC will be needed for about 30min with a 50-100nA current. In a nutshell:
 
**DAQ work. The goal is to optimize DAQ performance and find DAQ rate bottlenecks: data rate, trigger rate, live time. Several parameters have to be defined for every DAQ components independently: detectors readout (for FDC,CDC,FCAL,BCAL,...), event builder, data concentrators, event recorder, to find the slowest. Optimization includes different triggers and beam current. FDC/CDC will be needed for about 30min with a 50-100nA current. In a nutshell:

Revision as of 12:55, 5 October 2015

General information

Weekly Meetings, TBD, Hall D conference room. Held by the Run Coordinator. Present Run Coordinator: Alexandre Deur

Connect Information

To connect from the outside by phone please do the following

1.) To join via a Web Browser, go to the page [1] https://bluejeans.com/660743227.

2.) To join via Polycom room system go to the IP Address: 199.48.152.152 (bjn.vc) and enter the meeting ID: 660743227.

3.) To join via phone, use one of the following numbers and the Conference ID: 660743227.

4.) The moderator code is 8394

Dial Either +1 408 740 7256 or +1 888 240 2560 for US or Canada

4.) More information on connecting to bluejeans is available. The old ESNET and SeeVough Information is archived here.

Specific instructions for connecting from JLab's Hall D conference room:

  • Turn polycom on if necessary (do it before turning the computer on)
  • With the polycom, place a call at 199.48.152.152
  • Press # to enable the polycom keypad, then enter the meeting id: 660743227 and #
  • You may have to unmute the microphone: #*4
  • Turn the computer on if needed

Meeting General Agenda

September 22, 2015

Present: E. Chudakov, A. Deur, C. Meyer, M. Shepherd, E. Smith.

There will be five weeks of beam operations, out of which there will be at least one week of beam restoration (probably more) starting on Nov. 9th. From discussion with Arne F., it is unlikely that we will get beam before Thanksgiving. In addition, we will have the Hall open during the day for 2 weeks or more for the magnet according to Ben Z. At least one week will overlap with the beam restoration. According to that, we would have at most 4 weeks of possible beam with 12 GeV priority including 1 week or more with beam only during owl and night shifts, if the accelerator agrees (Hall availability to the 12 GeV has priority over the magnet repair).

  • Run condition:
    • No magnetic field. Unless accelerators requires it, Hall is open during day (7am-4pm ?) for solenoid repairs.
    • 5mm collimator will be used.
    • The target will remain in gaseous state so that there is no need to man the counting room. Events will come from the solid targets/window on the beam line (1mm CH2 disk on the nose of the ST and 100 μm Al. 2cm downstream of the CH2). If we need a liquid target, we should warn the target group two days in advance (for courtesy. Cooling down the target takes only 5 to 6h). Do we need to install a thicker solid target ?
    • Stand-by shifts from November 30 until December 13. No foreign groups included to limit their travel costs.
    • FDC off (Lubomir P: we should not run the FDC without magnetic field because the high drawn current accelerates the aging of the detector).
    • All other detectors on (required for DAQ and trigger studies). All beamline equipment on except TAC.
    • When accelerator is ready to start its fast feedback commissioning, it needs to be coordinated with solenoid work, which requires the Hall (and thus the tagger) to be open Can all/most of the solenoid work be done in Controlled Access?.


  • list of tasks for the Fall 2015 run:
    • 4 hours for 10 days for Fast-Feedback Studies (Accelerator responsibility: Trent Allison, Brian Bevins). There will be no need to man our counting room. Will they do the 5nA tests?
    • Beam line model test. (Expected time unknown, Accelerator responsibility: Todd Satogata). Is this still in the plan?
    • Tagger detectors commissioning (Hall D responsibility: Richard J. and Alex B.). Detailed plan needed from Richard J. and Alex B.
    • Alex S.needs as much data as possible on the PS and tagger detectors, as well as for trigger studies. Alex claims that for his basics investigation, no having the magnetic field doesn't matter. We will need to have the calorimeters, SC and TOF on during theses studies. (Hall D responsibility: Alex S.). Detailed plan needed from Alex S.
    • Sergey F. needs to have dedicated DAQ time (a couple hours/day) since he did not get enough data in May. (Hall D responsibility: Sergey F.). The goal is to optimize DAQ performance : data rate, trigger rate, live time. Several parameters have to be defined for every DAQ components independently: detectors readout (for FDC,CDC,FCAL,BCAL,...) , event builder, data concentrators, event recorder, to find the slowest. Optimization includes different triggers and beam currents.
    • Lubomir P. and Sergei F. would like to test their transition radiation set-up. It should be parasitic to other Hall D activities, but it may require a specific trigger at some point. (Hall D responsibility: Lubomir P., Sergey F.). Need details from Sergey F. .
    • Calorimeters, ST and TOF will take data (for their sake and because of the trigger/DAQ studies).


  • List of tasks that cannot be done during the Fall 2015 run:
    • Goniometer and polarimeter commissioning.
    • Total Absorption Counter commissioning.

October 02, 2015

Present:Alex B., Alexandre D., David L., Curtis M., Matt S., Elton S., Alex. S.

  • When to start readiness meetings? HCO?. We can start with a weekly 8:45 meeting, after the collaboration meeting. HCO can start beginning of November.
  • We do not expect to have beam before after Thanksgiving before starting operations involving Hall D. There are 4 scenarios:
    • Miracle scenario: everything is proceeding without any hitch. Then the beam could be ready before Thanksgiving.
    • Realistic good scenario: everything is proceeding as expected. Beam comes around Thanksgiving. We have the 10 first days busy with FFb commissioning. The remaining few days of swing and night shifts will be for Hall D commissioning
    • Realistic bad scenario: the 12 GeV goal is reached near mid-December. There will be no beam in the tagger or in Hall D. FFB commissioning is postponed to Spring 16.
    • Really bad scenario: the 12 GeV goal cannot reached. Accelerator would switch to Hall operation at lower energy. Depending on when accelerator decides that 12 GeV cannot reached for Fall, we may get beam availability before Thanksgiving.
  • Run conditions:
    • Target: Cryotarget will not be cooled down. We should install the 10mm disk of CH2 (HDPE, high density polyethylene) on the ST nose. Tim W. has been contacted about this.
    • Hardware and softwares for the fast feedback commissioning are close to be ready. They should be ready for the Fall run with plenty of safetey margin.
    • Can all/most of the solenoid work be done in Controlled Access?
    • Once the FFB commissioning start, there will still a priori be no need to man the counting room until radiators need to be inserted (end of the commissioning involving the Active Collimator). Gain changes for the Active Collimator will be handled by the accelerator. Richard J. and Alex B. to provide Trent A. and Brian B with a procedure. However, the FFB tests will likely be followed by a few hours of beam for Hall D use. The counting room will need to be staffed then. Probably, we will need to have night active shifts and standby day and swing shifts.
  • Schedule, list of tasks:
    • We do not expect to have beam until after Thanksgiving.
    • Before starting operations involving Hall D:
      • Hot Checkout update
      • 12 GeV beam must be established.
      • Probably, high current run (100μA) will then occur (beam in Hall A) to test cavity loading.
    • FFB commissioning: The test will start at 1μA, and possibly 3μA. RadCon has been notified. No radiator will be in place but, due to the nature of the commissioning, beam scrapping will occur. ⇒ We must be sure that the Ion Chambers are properly calibrated and their threshold properly set before to start the commissioning. Since the beam will be shut down quickly, no special additional shielding or precautions need to be taken for the tagger electronic.
    • Beam tuning for FFB commissioning will start in the evening. Then a few hours of FFB will follow. The rest of the night will be available for other Hall D commissioning tasks.
    • FFB commissioning will be concluded by low current (5nA) nA-BPM commissioning.
    • Beam line FOPT. About 2h of data. Data for beam energy stability study will be gathered at the same time.
    • Tagger detector commissioning (parasitic to FFB work). Alex. B. and Richard J. provided a test plan.
    • Trigger tests
    • DAQ work. The goal is to optimize DAQ performance and find DAQ rate bottlenecks: data rate, trigger rate, live time. Several parameters have to be defined for every DAQ components independently: detectors readout (for FDC,CDC,FCAL,BCAL,...), event builder, data concentrators, event recorder, to find the slowest. Optimization includes different triggers and beam current. FDC/CDC will be needed for about 30min with a 50-100nA current. In a nutshell:
      • The detectors will be running the same hardware (no new fiber bundles for Fall15) and software as the previous run.
      • Before the start of the run, there may be a 2h work in the tagger Hall If some microscope control boards need to be replaced with the now available spares. (Alex B.)
      • Bias voltage study with 2 voltage settings. About 2×40min of data taking if we get about 1kHz PS trigger rate. This can be done parasitically to the FFB work.
      • Collect about 4h of data (should provide 1M events).
      • Possibly: fiber alignment checks (Alex. B to let us know if it is necessary and how long it would take)
    • Trigger tests at high current (μA): Alex S.
    • Lubomir P. and Sergei F.: transition radiation studies.