Difference between revisions of "October 22, 2018 DIRC"

From GlueXWiki
Jump to: navigation, search
(Agenda)
(Agenda)
Line 34: Line 34:
 
#* Finalizing DIRC "as-built" geometry: support frames, bar box internals, etc. (Yunjie)
 
#* Finalizing DIRC "as-built" geometry: support frames, bar box internals, etc. (Yunjie)
 
#* LED generator (Yunjie)
 
#* LED generator (Yunjie)
#* Time-based studies (Maria)
+
#* Time-based studies (Maria [https://gluexdirc.mit.edu/sim-update-1 1] [https://gluexdirc.mit.edu/dirc-time-imaging-reco 2] [https://gluexdirc.mit.edu/dirc-time-imaging-reco-2-png 3])
 
#* Alignment updates (Cris)
 
#* Alignment updates (Cris)
 
#* Software [https://halldweb.jlab.org/wiki/index.php/DIRC_Software_Overview overview] and [https://halldweb.jlab.org/wiki/index.php/DIRC_Software_Tasks tasks] (All)
 
#* Software [https://halldweb.jlab.org/wiki/index.php/DIRC_Software_Overview overview] and [https://halldweb.jlab.org/wiki/index.php/DIRC_Software_Tasks tasks] (All)

Revision as of 12:45, 22 October 2018

Meeting Information

GlueX DIRC Meeting
Monday October 22, 2018
1:00 pm, EDT
JLab room A110

Connection Using Bluejeans

  1. To join via Polycom room system go to the IP Address: 199.48.152.152 (bjn.vc) and enter the meeting ID: 846453895.
  2. To join via a Web Browser, go to the page [1] https://bluejeans.com/846453895 .
  3. To join via phone, use one of the following numbers and the Conference ID: 846453895
    • US or Canada: +1 408 740 7256 or
    • US or Canada: +1 888 240 2560
  4. More information on connecting to bluejeans is available.

Agenda

  1. Announcements
    • Updated schedule from JLab management, full energy running until 11/26
    • CompCal is priority for Fall, and will likely be installed during shorter downtimes leading up to Thanksgiving
  2. Optical box
    • Fabrication status update (Ernie and Jason)
      • Box window flange modification at Lesker (Ernie/Tim)
      • Dark box enclosure: fabrication and testing (Jason)
      • Quartz window (with modified flange) (Ernie)
    • Testing in ESB
    • Testing in EEL 226
  3. DAQ integration
  4. Slow controls
  5. Software/simulations
    • Finalizing DIRC "as-built" geometry: support frames, bar box internals, etc. (Yunjie)
    • LED generator (Yunjie)
    • Time-based studies (Maria 1 2 3)
    • Alignment updates (Cris)
    • Software overview and tasks (All)
  6. Addressing ERR review recommendations
    • Recommendations pertaining to Fall 2018 DIRC commissioning should be addressed before October installation (required for new beam time request)
  7. AOB