Difference between revisions of "October 21, 2021 CPP Design Meeting"

From GlueXWiki
Jump to: navigation, search
(Agenda)
(Agenda)
Line 11: Line 11:
 
** Lead absorbers - out for bid
 
** Lead absorbers - out for bid
 
** All assembly hardware wither here or due in by December
 
** All assembly hardware wither here or due in by December
* Installation/assy 3D Model and dwgs
 
*** DS Chamber orientation?
 
*** Scintillator orientation?
 
*** assembly components - drawings released
 
*** Installation drawings in review
 
 
** Stand All parts here -assembled in the TEDF High bay [[image:cpp_stand_5.jpg|thumb]]  
 
** Stand All parts here -assembled in the TEDF High bay [[image:cpp_stand_5.jpg|thumb]]  
 
** Steel - all received [[image:cpp_steel_3.jpg|thumb]]
 
** Steel - all received [[image:cpp_steel_3.jpg|thumb]]
** Fcal platform mods
+
* Installation/assy 3D Model and dwgs
*** Cutouts complete
+
** DS Chamber orientation?
*** Floor Rails installed and aligned [[image:cpp_rails.jpg|thumb]]
+
** Scintillator orientation?
 +
** assembly components - drawings released
 +
** Installation drawings in review
 +
* Target Design in work
 +
 
 
* Things to work out
 
* Things to work out
 
** Gas system, manifold/bubblers (Beni has some)
 
** Gas system, manifold/bubblers (Beni has some)

Revision as of 14:31, 21 October 2021

Meeting Time and Place

Thursday October 21, 2021, 3:00pm Bluejeans https://bluejeans.com/465620466

  • Present - Elton, Dave, Stephanie, Ilya, Rory, Mark S, Beni, Simon, Mark I

Agenda

  • Minutes from last meeting https://halldweb.jlab.org/wiki/index.php/September_09,_2021_CPP_Design_Meeting
  • Testing status - Beni/Elton
  • Design/Fab/Procurement status
    • Lead absorbers - out for bid
    • All assembly hardware wither here or due in by December
    • Stand All parts here -assembled in the TEDF High bay
      Cpp stand 5.jpg
    • Steel - all received
      Cpp steel 3.jpg
  • Installation/assy 3D Model and dwgs
    • DS Chamber orientation?
    • Scintillator orientation?
    • assembly components - drawings released
    • Installation drawings in review
  • Target Design in work
  • Things to work out
    • Gas system, manifold/bubblers (Beni has some)
    • Complete structural analysis - approved by Tom Renzo - need to release into system
    • Develop Detailed installation plan
    • Develop Design/operational/Maintenance Requirements
    • Modified US vacuum system
    • Solid target installation
    • Installation drawing including Microscope move
    • CPP Detector operations in Hall D OSP
    • Possible use of nitrogen flow for cooling electronics in Faraday cage

Minutes and Action Items

Action Items