== Agenda ==
 
== Agenda ==
* Minutes from last meeting https://halldweb.jlab.org/wiki/index.php/October_07,_2022_FCAL_Insert_Installation_Meeting
+
* Minutes from last meeting https://halldweb.jlab.org/wiki/index.php/September_21,_2022_FCAL_Insert_Installation_Meeting
 
* Discuss Lead Glass and crystal module removal/install] - Sasha
 
* Discuss Lead Glass and crystal module removal/install] - Sasha
 
* Use of platform upstream of detector - Stephanie/Tim
 
* Use of platform upstream of detector - Stephanie/Tim
Line 12: Line 12:
 
** New Cables
 
** New Cables
 
* Cable quotes 0 Chris S.
 
* Cable quotes 0 Chris S.
 +
* Existing structure can support 2500lbs
 
* Monitoring system discussion directly after
 
* Monitoring system discussion directly after
 
* Assembly in ESB
 
* Assembly in ESB
Line 21: Line 22:
 
[[image:Work_platform_top.png|thumb]]
 
[[image:Work_platform_top.png|thumb]]
 
[[image:Work_platform_iso.png|thumb]]
 
[[image:Work_platform_iso.png|thumb]]
[[image:Work_platform_bird|thumb]]
+
[[image:Work_platform_bird.png|thumb]]
  
 
== Minutes ==
 
== Minutes ==
 +
* Discussed lead glass module removal/install
 +
** Lead glass blocks will be installed as they are now with alternating SS vertical and then horizontal
 +
** Refurbishing existing module bases is about 1 hour for Malte and Mark, but Chris S. also has to do very delicate work also
 +
** Students may help  base repairs but ES&H input would be needed
 +
** Since there is no time to design, test and fabricate new bases for the existing modules, we will stick to repairing existing bases
 +
** The worst bases should be removed in March before taking apart the detector so the repairs can be started
 +
** More detail needed on existing module refurbish plan
 +
** Mark D. has database for existing module and will come up with an initial plan for sorting
 +
** Existing cables that may be used need to be relabeled and put in database
 +
** Eugene expressed that we should work with the mini FCAL to develop the removal/refurbish plan
 +
 +
* Cable discussions
 +
** Fernando expressed that in the tight area, LV cables should not be ribbon cables - 1 cable for each base should be used
 +
** Revisited signal cable plan to come from downstream wall through patch panel - Mark D. not at previous meeting - seems ok
 +
** Six patch panels in all for all new cables - need to start designing this for dark room and reinforcements needed
 +
** Existing I-beam over dark room should handle additional cable weight
 +
** Need to look at cable routing under platform and come up with a layout
 +
** Sasha needs to come up with a cable mapping plan to help reach decisions on using existing cables or removing all
 +
** Chris S. will ship out 1200 signal cables to get terminated
 +
** Chris S. to get quote on additional 400 signal cables
 +
** Chris already request quote for 1600 new thin (RG174) signal cables to go from patch panel to detectors
 +
* Looked at using the existing BCAL install platform on the upstream side of the FCAL.
 +
** We should probably use this regardless of decision to remove cables from crates
 +
** Can we use scaffolding on the temporary platform?
 +
* Discussed insulation vacuum vs. standard - standard foam board ok since delta T is small
 +
 +
* Discussed monitoring panel design for the crystals in a separate meeting
 +
** Arshak showed his testing and baseline design
 +
*** Optical fibers coming in on all 4 outer edges (120 fibers for now)
 +
*** 1/2" acrylic sheet in 2 pieces
 +
** Discussed how to route fibers
 +
*** through holes in FCAL2 step frames - bushings needed
 +
*** route over glass module monitoring panel
 +
*** maybe have fiber connections at upstream surface and install with rohacell backbone and tungsten absorber as an assembly
 +
*** is there 90° connectors for fibers or generous bend radius needed?
 +
** Discussed supporting outer edges of panel to rohacell for stability
  
 
== Action Items ==
 
== Action Items ==
 +
* Send out 1200 signal cables to get terminated - Chris S.
 +
* Start looking at how to use the existing database for lead glass handling - Mark D
 +
* Update baseline schedule with additional items discussed - Scot
 +
* Come up with a written cable mapping plan - Sasha
 +
* Update 3D model for patch panels - Stephanie
 +
* Develop cable routing plan under platform - Tim/Scot/Stephanie
 +
* Check on use of scaffolding on the platform - Scot
 +
* Continue with monitoring panel design - Arshak, Stephanie, Tim, Keith

Latest revision as of 14:51, 11 October 2022

Meeting Time and Place

Wednesday October 05, 2022 10am At Jefferson Lab, Hall D Counting House and on Teams

Agenda

Lower step.jpeg
JBweld cooling test.jpeg
Glass module steps.jpeg
Work platform.png
Work platform top.png
Work platform iso.png
Work platform bird.png

Minutes

  • Discussed lead glass module removal/install
    • Lead glass blocks will be installed as they are now with alternating SS vertical and then horizontal
    • Refurbishing existing module bases is about 1 hour for Malte and Mark, but Chris S. also has to do very delicate work also
    • Students may help base repairs but ES&H input would be needed
    • Since there is no time to design, test and fabricate new bases for the existing modules, we will stick to repairing existing bases
    • The worst bases should be removed in March before taking apart the detector so the repairs can be started
    • More detail needed on existing module refurbish plan
    • Mark D. has database for existing module and will come up with an initial plan for sorting
    • Existing cables that may be used need to be relabeled and put in database
    • Eugene expressed that we should work with the mini FCAL to develop the removal/refurbish plan
  • Cable discussions
    • Fernando expressed that in the tight area, LV cables should not be ribbon cables - 1 cable for each base should be used
    • Revisited signal cable plan to come from downstream wall through patch panel - Mark D. not at previous meeting - seems ok
    • Six patch panels in all for all new cables - need to start designing this for dark room and reinforcements needed
    • Existing I-beam over dark room should handle additional cable weight
    • Need to look at cable routing under platform and come up with a layout
    • Sasha needs to come up with a cable mapping plan to help reach decisions on using existing cables or removing all
    • Chris S. will ship out 1200 signal cables to get terminated
    • Chris S. to get quote on additional 400 signal cables
    • Chris already request quote for 1600 new thin (RG174) signal cables to go from patch panel to detectors
  • Looked at using the existing BCAL install platform on the upstream side of the FCAL.
    • We should probably use this regardless of decision to remove cables from crates
    • Can we use scaffolding on the temporary platform?
  • Discussed insulation vacuum vs. standard - standard foam board ok since delta T is small
  • Discussed monitoring panel design for the crystals in a separate meeting
    • Arshak showed his testing and baseline design
      • Optical fibers coming in on all 4 outer edges (120 fibers for now)
      • 1/2" acrylic sheet in 2 pieces
    • Discussed how to route fibers
      • through holes in FCAL2 step frames - bushings needed
      • route over glass module monitoring panel
      • maybe have fiber connections at upstream surface and install with rohacell backbone and tungsten absorber as an assembly
      • is there 90° connectors for fibers or generous bend radius needed?
    • Discussed supporting outer edges of panel to rohacell for stability

Action Items

  • Send out 1200 signal cables to get terminated - Chris S.
  • Start looking at how to use the existing database for lead glass handling - Mark D
  • Update baseline schedule with additional items discussed - Scot
  • Come up with a written cable mapping plan - Sasha
  • Update 3D model for patch panels - Stephanie
  • Develop cable routing plan under platform - Tim/Scot/Stephanie
  • Check on use of scaffolding on the platform - Scot
  • Continue with monitoring panel design - Arshak, Stephanie, Tim, Keith