== Minutes ==
 
== Minutes ==
 
+
* Briefly discussed minutes from December meeting
 +
* Reviewed Igor's geometry layout
 +
* Determined 6cm ID tube from collimator wall to target - wall thickness will be 1.5 to 2 mm, ok
 +
* Determined Flux monitor downstream edge is 4m from PS magnet center
 +
* Need to talk to Chris Keith about new 6cm cryo target - make sure there is room to pull it out
 +
* Mikhail present latest Flux monitor design
 +
** Need to remove PS shield wall
 +
** Look at fitting an MRI magnet on platform (5.5 tonnes)
 +
** Need to determine height to center of magnet
 +
** Will it fit on existing platform and is it strong enough?
 +
** Need to determine power requirements
 +
** 90 l/min LCW needed
 +
** Mikhail to send data sheet for magnet
 +
* Existing solenoid will be powered for the experiment* Igor to send link to KLON wiki https://wiki.jlab.org/klproject/index.php/Main_Page
  
 
== Action Items ==
 
== Action Items ==

Revision as of 16:32, 20 January 2022

Meeting Time and Place

Thursday January 20, 2022, 1pm Zoom https://jlab-org.zoomgov.com/j/1607996337?pwd=b1lEWVhDU0VjSG1DaEhPd0tVK0VjZz09&from=addon#success

  • Present - Hovanes Egiyan, Stephanie Worthington, Keith Harding, Igor Strakovsky, Tim Whitlatch, Mark Stevens, Vitaly

Agenda

Requirements and things to finalize

    • 5 cm beam tube through sweep magnet and 6 cm to final target
    • Remove PS vacuum chamber and put in 6cm beampipe

Minutes

  • Briefly discussed minutes from December meeting
  • Reviewed Igor's geometry layout
  • Determined 6cm ID tube from collimator wall to target - wall thickness will be 1.5 to 2 mm, ok
  • Determined Flux monitor downstream edge is 4m from PS magnet center
  • Need to talk to Chris Keith about new 6cm cryo target - make sure there is room to pull it out
  • Mikhail present latest Flux monitor design
    • Need to remove PS shield wall
    • Look at fitting an MRI magnet on platform (5.5 tonnes)
    • Need to determine height to center of magnet
    • Will it fit on existing platform and is it strong enough?
    • Need to determine power requirements
    • 90 l/min LCW needed
    • Mikhail to send data sheet for magnet
  • Existing solenoid will be powered for the experiment* Igor to send link to KLON wiki https://wiki.jlab.org/klproject/index.php/Main_Page

Action Items