Difference between revisions of "JEF meeting, May 26, 2023"

From GlueXWiki
Jump to: navigation, search
m
Line 1: Line 1:
eeting time and location:
+
Meeting time and location:
 
*9:30 am EST (JLab time) remote only
 
*9:30 am EST (JLab time) remote only
 
* [https://halldweb.jlab.org/wiki-private/index.php/JEF_Weekly_Meeting#Connection_information Connection information]
 
* [https://halldweb.jlab.org/wiki-private/index.php/JEF_Weekly_Meeting#Connection_information Connection information]

Revision as of 10:10, 1 June 2023

Meeting time and location:

Agenda

  • Preparation of parts for ECAL modules -- Sasha
    • Crystals:
      Received 50 crystals from CRYTUR [1]. Remaining 45 crystals are expected to be delivered to the Lab in May/June.
      Wrapped crystals during last week: 16
      Available for wrapping: 10 CRYTUR
    • Received 725 long signal cables
    • Procurement parts for the LMS:
      16,400 ft of optical fibers delivered to the lab. 7,600 will be delivered in September.
      Expect to receive all plastic caps for the LMS during next week
  • Module fabrication -- Sasha
  • Visual inspections of fabricated modules [2]
    -715 modules have been checked (273 SICCAS + 442 CRYTUR) [3]
  • Testing and labeling cables
  • Testing of PMT dividers -- Sasha / Vlad
    • Most parts for the active base have been arrived to the lab (including PCBs)
    • All dividers will be ordered during next week (by Chris S.)
  • Installation of the FCAL2 detector & integration to GlueX -- Sasha / Arshak
Discussion of the FCAL2 installation procedures [6]

Minutes

Attendees: Arshak, Liping, Sasha, Olga, Bill, Jon, Jane, S.T.

  • Crytur crystals still arriving at lab
    • Expect 10 more soon (45 remaining)
  • Signal cables arrived, need to be checked using cable tester
    • Need to pull 400 cables from Hall (also ordered 400 more cables, but lead time is very long)
  • Label maker arrived
  • Total number of fabricated modules now 1558
    • Visual inspections continue (715 inspected)
    • Next week begin testing modules
  • PMT divider saturation issue resolved, parts in place, boards to be sent out to outside company to populate with components (20 day lead time)
  • Module stacking test underway
    • No shims yet
    • Need to verify torque
  • Re-stacking to start July 11