Difference between revisions of "JEF meeting, March 4, 2022"

From GlueXWiki
Jump to: navigation, search
(Agenda)
(Agenda)
Line 10: Line 10:
 
*** [https://halldweb.jlab.org/wiki-private/index.php/PMT_for_FCAL_insert quite a few PMTs have to be exchanged with NPS]
 
*** [https://halldweb.jlab.org/wiki-private/index.php/PMT_for_FCAL_insert quite a few PMTs have to be exchanged with NPS]
 
*** Two fixtures (42 cookies in each) and digital scales have been ordered. The loan agreement with GWU  will be submitted for approval in the beginning of next week.  
 
*** Two fixtures (42 cookies in each) and digital scales have been ordered. The loan agreement with GWU  will be submitted for approval in the beginning of next week.  
 +
** Igal is cutting Tedlar and Kapton
 
** Some backlog with brazing straps, communicated with Tim and Mark regarding getting Chris more involved.
 
** Some backlog with brazing straps, communicated with Tim and Mark regarding getting Chris more involved.
 
** Quite a few mu-metal housings are tight (no space for kapton film)  have to be 'polished', met with Tim
 
** Quite a few mu-metal housings are tight (no space for kapton film)  have to be 'polished', met with Tim

Revision as of 10:18, 4 March 2022

Meeting time and location

  • 9:30 am EST (JLab time) remote only
  • Zoom meeting ID: 161 050 9142 Passcode: 004965

Agenda

  • Preparation for mass production of FCAL2 modules -- Sasha
    • DSG has preshaped more than 200 ESR foils, had a meeting today regarding wrapping crystals
    • Olga visited JLab: prepared 3 sets of Silicon cookies and tested diameter of about 300 PMTs
    • Igal is cutting Tedlar and Kapton
    • Some backlog with brazing straps, communicated with Tim and Mark regarding getting Chris more involved.
    • Quite a few mu-metal housings are tight (no space for kapton film) have to be 'polished', met with Tim
  • Module fabrication -- Sasha
  • Light Monitoring System
  • COMCAL tests, TAC running, etc.
  • Data analysis
  • Simulations