* Preparation for mass production of FCAL2 modules -- Sasha
 
* Preparation for mass production of FCAL2 modules -- Sasha
 
** DSG has preshaped about 300 ESR foils. Started wrapping crystals with the ESR and Tedlar (first 10 modules wrapped)
 
** DSG has preshaped about 300 ESR foils. Started wrapping crystals with the ESR and Tedlar (first 10 modules wrapped)
** Chris continues to make brass strap assemblies
+
** Loan agreement with GWU submitted for signatures. Two fixtures for silicon cookies were ordered. Olga is planning to come to Jlab
 +
** Chris continues to braze brass strap assemblies
 
** Bobby has started working on honing soft iron PMT housing (some mu-metal cylinders don't fit into PMT housings)  
 
** Bobby has started working on honing soft iron PMT housing (some mu-metal cylinders don't fit into PMT housings)  
 
* Module fabrication  -- Sasha
 
* Module fabrication  -- Sasha

Revision as of 00:34, 11 March 2022

Meeting time and location

  • 9:30 am EST (JLab time) remote only
  • Zoom meeting ID: 161 050 9142 Passcode: 004965

Agenda

  • Preparation for mass production of FCAL2 modules -- Sasha
    • DSG has preshaped about 300 ESR foils. Started wrapping crystals with the ESR and Tedlar (first 10 modules wrapped)
    • Loan agreement with GWU submitted for signatures. Two fixtures for silicon cookies were ordered. Olga is planning to come to Jlab
    • Chris continues to braze brass strap assemblies
    • Bobby has started working on honing soft iron PMT housing (some mu-metal cylinders don't fit into PMT housings)
  • Module fabrication -- Sasha
  • Light Monitoring System
  • COMCAL tests, TAC running, etc.
  • Data analysis
  • Simulations
  • FCAL2 Insert Efficiency in Phi -- Azizah