** Most parts for the active base have been arrived to the lab (including PCBs)
 
** Most parts for the active base have been arrived to the lab (including PCBs)
 
** All dividers will be ordered during next week (by Chris S.)
 
** All dividers will be ordered during next week (by Chris S.)
 +
** [https://halldweb.jlab.org/wiki/index.php/FCAL_Insert_Module_Fabrication Proceedures]
 
* '''Installation of the FCAL2 detector & integration to GlueX''' -- Sasha / Arshak
 
* '''Installation of the FCAL2 detector & integration to GlueX''' -- Sasha / Arshak
 
** [https://halldweb.jlab.org/wiki/index.php/FCAL_Installation Detector installation page]
 
** [https://halldweb.jlab.org/wiki/index.php/FCAL_Installation Detector installation page]

Revision as of 09:26, 2 June 2023

Meeting time and location:

Agenda

Preparation of parts for ECAL modules -- Sasha

    • Crystals:
      Received 60 crystals from CRYTUR [1]. Remaining 35 crystals are expected to be delivered to the Lab in May/June.
      Wrapped crystals during last week: 16
      Available for wrapping: 10 CRYTUR
    • Received 875 long signal cables
    • Procurement parts for the LMS:
      16,400 ft of optical fibers delivered to the lab. 7,600 will be delivered in September.
      Expect to receive all plastic caps for the LMS during next week
  • Module fabrication -- Sasha
  • Visual inspections of fabricated modules [2]
    -1058 modules have been checked (273 SICCAS + 785 CRYTUR) [3]
  • Testing and labeling cables
  • Removing signal cables from the FCAL [5]
  • Testing of PMT dividers -- Sasha / Vlad
    • Most parts for the active base have been arrived to the lab (including PCBs)
    • All dividers will be ordered during next week (by Chris S.)
    • Proceedures
  • Installation of the FCAL2 detector & integration to GlueX -- Sasha / Arshak
Discussion of the FCAL2 installation procedures [7]