JEF meeting, February 18, 2022

From GlueXWiki
Revision as of 22:26, 17 February 2022 by Somov (Talk | contribs) (Agenda)

Jump to: navigation, search

Meeting time and location

  • 9:30 am EST (JLab time) remote only
  • Zoom meeting ID: 161 050 9142 Passcode: 004965

Agenda

  • Preparation for mass production of FCAL2 modules -- Sasha
    • got 6 more fixtures from NPS to preshape ESR. 16 fixtures can be loaded to the oven now. Expected DSG production rate: up to 80 foils per week
      • Regular meeting with the DSG group during next week. Try to coordinate crystal wrapping.
    • Arshak and Sasha are working on preparing supplies.
      • Silicon cookies
      • Light guides
      • Matching PMT housing and mu-metal cylinders (sorting out cylinder by the diameter). Some housing/cylinders are tight. Had a meeting with Tim regarding 'machining' the hole in the PMT housing.
    • Igal is cutting Kapton, ESR (for LG), and mu-metal
    • Chris A. continues brazing brass strips; we are running short with them (Chris is involved in the CPP installation). Trying to get him more involved (discussing with Tim and Mark)
  • Module fabrication -- Sasha
  • Light Monitoring System
  • COMCAL tests, TAC running, etc.
  • Data analysis
  • Simulations