* Preparation for mass production of FCAL2 modules -- Sasha
 
* Preparation for mass production of FCAL2 modules -- Sasha
 
**  got 6 more fixtures to preshape ESR. 16 fixtures can be loaded to the oven now. Expected DSG production rate: up to 72 foils per week
 
**  got 6 more fixtures to preshape ESR. 16 fixtures can be loaded to the oven now. Expected DSG production rate: up to 72 foils per week
***  Regular meeting with the DSG group during next week. Try to coordinate crystal wrapping.  
+
***  Regular meeting with the DSG group during next week. Try to coordinate crystal wrapping.
 +
** Arshak and Sasha are working on preparing supplies.
 +
*** 
 
* Module fabrication  -- Sasha
 
* Module fabrication  -- Sasha
 
** [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/module_fabrication.pdf  Modules fabricated by Arshak and Sasha ] [https://docs.google.com/document/d/1upI9M_RNR4qipzwg-SmxmzkqoCDU294x7Y3jT5M6DVY/edit (list on Google Drive)] [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/2_17_22/fab_mod_2_17_22.jpg Fabricated modules in TEDF ]
 
** [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/module_fabrication.pdf  Modules fabricated by Arshak and Sasha ] [https://docs.google.com/document/d/1upI9M_RNR4qipzwg-SmxmzkqoCDU294x7Y3jT5M6DVY/edit (list on Google Drive)] [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/2_17_22/fab_mod_2_17_22.jpg Fabricated modules in TEDF ]

Revision as of 22:05, 17 February 2022

Meeting time and location

  • 9:30 am EST (JLab time) remote only
  • Zoom meeting ID: 161 050 9142 Passcode: 004965

Agenda

  • Preparation for mass production of FCAL2 modules -- Sasha
    • got 6 more fixtures to preshape ESR. 16 fixtures can be loaded to the oven now. Expected DSG production rate: up to 72 foils per week
      • Regular meeting with the DSG group during next week. Try to coordinate crystal wrapping.
    • Arshak and Sasha are working on preparing supplies.
  • Module fabrication -- Sasha
  • Light Monitoring System
  • COMCAL tests, TAC running, etc.
  • Data analysis
  • Simulations