February 17, 2022 KLONG Phase II Design Meeting

From GlueXWiki
Revision as of 16:11, 16 February 2022 by Whitey (Talk | contribs) (Requirements and things to finalize)

Jump to: navigation, search

Meeting Time and Place

Thursday February 17, 2022, 1pm

Zoom https://jlab-org.zoomgov.com/j/1611857466?pwd=VEZndTZzdDdNOUdJU3NxblRLcVoxdz09&from=addon

  • Invited - Hovanes Egiyan, Stephanie Worthington, Keith Harding, Igor Strakovsky, Tim Whitlatch, Vitaly Baturin,

Mikhail Bashkanov, Anthony Palazzo, Eugene Chudakov, Mark Stevens

Agenda

Phase II is the section downstream of the collimator cave shield wall through the liquid target

Requirements and things to finalize

Minutes

  • Briefly discussed minutes from December meeting
  • Reviewed Igor's geometry layout
  • Determined 6cm ID tube from collimator wall to target - wall thickness will be 1.5 to 2 mm, ok
  • Need to talk to Chris Keith about new 6cm cryo target - make sure there is room to pull it out
  • Mikhail present latest Flux monitor design
    • Need to remove PS shield wall
    • Look at fitting an MRI magnet on platform (5.5 tonnes)
    • Need to determine height to center of magnet
    • Will it fit on existing platform and is it strong enough?
    • Need to determine power requirements
    • 90 l/min LCW needed
    • Mikhail to send data sheet for magnet
  • Existing solenoid will be powered for the experiment
  • link to KLF wiki https://wiki.jlab.org/klproject/index.php/Main_Page
  • Vitaly added the following after the meeting
    • 1. I've imported the Source Model (FLUKA) that I received from Hovanes.
    • 2. For the moment it runs only without a magnetic field.
    • 3. FLUKA complaints that it can not open the file "cps_mag00.txt"
    • 4. This file is missing in *.zip file !

Hovanes, could you please get this file from the author of this model?

Action Items

  • Talk to Chris Keith about new cryo target - Tim
  • Layout geometry based on today's discussion
  • Set up future meetings