Fall 2014 Commissioning Simulations
From GlueXWiki
Contents
Overview
This page is for the organization and sharing of information about simulations for the Fall 2014 Commissioning data.
General Info
To Do Items
- Incoherent beam in bggen
- Commissioning target geometry in HDDS/sim-recon
- Confirm that the simulation of EM background in HDGeant works for this running
- What gate should be used?
- Decide which version of sim-recon should be used
Conditions
- New tagged sim-recon release?
- Other software versions
- Solenoid @ 1200 A
- Unpolarized photon beam <10 MHz/GeV at the endpoint
EM Background Simulations
- What is the background rate with no target?
- What is the background rate with various targets?
Hadronic Event Simulations
Overall hadronic rate
Reference: Fall 2014 Commissioning Plan
Assume 50 nA CW electron beam
1.5 µm Al | 10 µm Al | 30 µm Al | |
10mm CH2 | |||
2mm CH2 | |||
2/7mm CH2 | |||
3.4mm graphite |