Construction plan 1/1/2020 - 30/8/2020

From GlueXWiki
Revision as of 19:29, 8 January 2020 by Somov (Talk | contribs)

Jump to: navigation, search

The goal is to assemble 450 - 500 modules by the end of summer


  • Brazing straps
Procedure - brazing setup exists, has to be finalized
Time per module - 30 min


  • ESR shaping
- ESR cutting (cutting tool exist)
- Shaping in the oven (2 shaping tools exist, 30 min per cycle]


  • Tedlar cutting
- Tool exists
- Time per module - 15 min


  • Crystal wrapping
- Tool exists
- Time per module - 20 min


  • Preparation of silicon cookie
- Tool in preparation
- Mix RTV
- Pour to the gluing fixture
- wait 1 day to set, move to the oven for several hours
- Time: 2-3 days per 30 cookies


  • Module fabrication
- Time per module: 30 min