Difference between revisions of "Construction plan 1/1/2020 - 30/8/2020"

From GlueXWiki
Jump to: navigation, search
Line 26: Line 26:
 
::  - Tool in preparation
 
::  - Tool in preparation
 
::  - Mix RTV
 
::  - Mix RTV
::  -   
+
::  - Pour to the gluing fixture
 +
:: - wait 1 day to set, move to the oven for several hours
 +
:: - Time:  2-3 days per 30 cookies
  
  
 
* Module fabrication
 
* Module fabrication
 
::
 
::

Revision as of 19:27, 8 January 2020

The goal is to assemble 450 - 500 modules by the end of summer


  • Brazing straps
Procedure - brazing setup exists, has to be finalized
Time per module - 30 min


  • ESR shaping
- ESR cutting (cutting tool exist)
- Shaping in the oven (2 shaping tools exist, 30 min per cycle]


  • Tedlar cutting
- Tool exists
- Time per module - 15 min


  • Crystal wrapping
- Tool exists
- Time per module - 20 min


  • Preparation of silicon cookie
- Tool in preparation
- Mix RTV
- Pour to the gluing fixture
- wait 1 day to set, move to the oven for several hours
- Time: 2-3 days per 30 cookies


  • Module fabrication