:: - ESR cutting  (cutting tool exist)
 
:: - ESR cutting  (cutting tool exist)
 
:: - Shaping in the oven (2 shaping tools exist, 30 min per cycle]
 
:: - Shaping in the oven (2 shaping tools exist, 30 min per cycle]
 +
 +
 +
* Tedlar cutting
 +
:: - Tool exists
 +
:: - Time per module - 15 min
 +
 +
 +
* Crystal wrapping
 +
:: - Tool exists
 +
:: - Time per module - 20 min
 +
 +
* Preparation of silicon cookie
 +
::  - Tool in preparation
 +
::  - Mix RTV
 +
::  - 
 +
 +
 +
* Module fabrication
 +
::

Revision as of 19:21, 8 January 2020

The goal is to assemble 450 - 500 modules by the end of summer


  • Brazing straps
Procedure - brazing setup exists, has to be finalized
Time per module - 30 min


  • ESR shaping
- ESR cutting (cutting tool exist)
- Shaping in the oven (2 shaping tools exist, 30 min per cycle]


  • Tedlar cutting
- Tool exists
- Time per module - 15 min


  • Crystal wrapping
- Tool exists
- Time per module - 20 min
  • Preparation of silicon cookie
- Tool in preparation
- Mix RTV
-


  • Module fabrication