Difference between revisions of "Construction plan 1/1/2020 - 30/8/2020"
From GlueXWiki
Line 1: | Line 1: | ||
+ | The goal is to assemble 450 - 500 modules by the end of summer | ||
+ | |||
+ | |||
+ | |||
+ | * Brazing straps | ||
+ | ::: Procedure - brazing setup exists, has to be finalized | ||
+ | ::: Time per module - 30 min | ||
+ | |||
* ESR shaping | * ESR shaping | ||
:: - ESR cutting (cutting tool exist) | :: - ESR cutting (cutting tool exist) | ||
− | :: - Shaping in the oven (2 shaping tools exist | + | :: - Shaping in the oven (2 shaping tools exist, 30 min per cycle] |
Revision as of 19:15, 8 January 2020
The goal is to assemble 450 - 500 modules by the end of summer
- Brazing straps
- Procedure - brazing setup exists, has to be finalized
- Time per module - 30 min
- ESR shaping
- - ESR cutting (cutting tool exist)
- - Shaping in the oven (2 shaping tools exist, 30 min per cycle]