CPP and NPP Run Conditions

From GlueXWiki
Revision as of 09:56, 15 March 2022 by Hovanes (Talk | contribs)

Jump to: navigation, search
Time estimates for Run Plan
Activity Duration (PAC Days) Current Target Collimator Radiator Comment
Full target (Production) 20 27 nA Pb (0.3 mm) 3.4 mm JD70-103 or JD70-107 Alternate 0/90 deg diamond configuration
Empty Target 1.5? 27 nA - 3.4 mm JD70-103 or JD70-107 Run at higher current?
Diamond Alignment 0.5? 20 nA? Pb (0.3 mm) 3.4 mm JD70-103 and JD70-107
Trigger Commissioning 1.4? 100 nA? Pb (0.3 mm) 3.4 mm JD70-103 or JD70-107
Beam Energy Calibration 0.1? 100 nA Pb (0.3 mm) 3.4 mm JD70-103 or JD70-107 Collimator Blocking for 5 min, periodically
TAC Runs 1.5? <2 nA - 3.4 mm JD70-103 or JD70-107