* [[Media:CPP NPP RunConditions.png | CPP and NPP Run Conditions]]
 
* [[Media:CPP NPP RunConditions.png | CPP and NPP Run Conditions]]
* Electron beam energy expected = 11.7 GeV based on the planned [https://www.jlab.org/sites/default/files/user-liaison/documents/Web20211122.1.pdf Experimental Schedule]
+
* Electron beam energy expected = 11.57 GeV based on the planned [https://www.jlab.org/sites/default/files/user-liaison/documents/Web20211122.1.pdf Experimental Schedule]
 
* Microscope will cover the range of [0.301-0.514] of the beam energy or [4.57-6.01 GeV]
 
* Microscope will cover the range of [0.301-0.514] of the beam energy or [4.57-6.01 GeV]
 
* Hall D solenoid will operate at its nominal field of 1350 A.
 
* Hall D solenoid will operate at its nominal field of 1350 A.

Revision as of 11:14, 6 June 2022

  • CPP and NPP Run Conditions
  • Electron beam energy expected = 11.57 GeV based on the planned Experimental Schedule
  • Microscope will cover the range of [0.301-0.514] of the beam energy or [4.57-6.01 GeV]
  • Hall D solenoid will operate at its nominal field of 1350 A.
  • Use the 750 um PS converter to collect sufficient PS triggers at low rate.
  • Pair Spectrometer magnet will be scaled down by 6/9 = 0.67 of its nominal field (569.4 A = 0.67x849.9 A)
Time estimates for Run Plan
Activity Duration (PAC Days) Duration (hours) Current Target Collimator Radiator Contact Comment
Full target (Production) 20 960 27 nA Pb (0.3 mm) 3.4 mm JD70-103 or JD70-107 Alternate 45, 45, 135, 135 deg diamond configuration (90%) with amorphous data (10%)
TOF, CDC HV Scans 0.2 10 27 nA - 3.4 mm AMO (1x10-4) Beni, Naomi Need time to assess data before updating settings. FCAL/BCAL trigger
Empty Target 1.5? 72 50 nA - 3.4 mm JD70-103 or JD70-107 Rory, Ilya, Andrew Take data at full-target current for normalization
Diamond Alignment 0.5? 24 20 nA Pb (0.3 mm) 3.4 mm JD70-103 and JD70-107 Hovanes
Trigger Commissioning 1? 48 100 nA? Pb (0.3 mm) 3.4 mm JD70-103 or JD70-107 Sasha
Lead Shield Alignment 0.2 10 30-100 nA Pb (0.3 mm) 3.4 mm JD70-103 or JD70-107 Ilya
Beam Energy Calibration 0.1? 5 100 nA Pb (0.3 mm) 3.4 mm JD70-103 or JD70-107 Alexandre Collimator Blocking for 5 min, periodically
Straight Track (Solenoid off) 0.5? 24 100 nA? Pb (0.3 mm) 3.4 mm JD70-103 or JD70-107 Simon, Lubomir Ramping magnet takes about a shift.
PS magnet at GlueX nominal current 0.1? 5 27 nA? Pb (0.3 mm) 3.4 mm JD70-103 or JD70-107 Sasha?
TAC Runs 1.5? 72 <2 nA - 3.4 mm AMO (2x10-5) Sasha
All Non-production total 5.6 269 - - - - -

Preparations and Schedule

  1. CPP DAQ/Monitoring Test Spring 2022
  2. CPP Run Coverage Summer 2022

Draft Commissioning Steps

  1. Set Solenoid (standard GlueX) and PS magnet to CPP values (CPP = 2/3 * nominal GlueX).
  2. Setup photon beam operation at 50 nA.
  3. Check microscope and hodoscope operation in new configuration
  4. Align diamond to 6 GeV coherent edge
  5. Check rates in microscope in new position
  6. Check radiation and backgrounds rates in Hall D with Pb target
    • Check rates and beam stability at 30 nA
    • Check currents and hit distributions in the MWPCs
  7. Preliminary trigger setup to be used during initial checks
  8. Complete a HV scan for the TOF, CTOF and CDC. Adjust voltages accordingly, especially those of the TOF in advance of trigger studies.
  9. Take data for adjustment of the FCAL PMT gains.
  10. Compare empty vs full target rates
  11. Adjustable Pb absorber (upstream of muon detector)
  12. Commission trigger
    • Charged Trigger (TOF)
    • Neutral Trigger (FCAL/BCAL)
    • Calibration triggers (CTOF, random, PS)
    • Compare empty/full trigger rates
  13. Start of Production
    • Take a TAC run close to start and one at end of run.
    • PS: Take data at the nominal GlueX setting for reference.
    • Beam energy calibration (Short, possible daily runs)