CPP Run Coverage Summer 2022

From GlueXWiki
Revision as of 08:24, 11 May 2022 by Elton (Talk | contribs)

Jump to: navigation, search
Time estimates for Run Plan
Activity Duration (PAC Days) Duration (hours) Current Target Collimator Radiator Comment
Full target (Production) 20 960 27 nA Pb (0.3 mm) 3.4 mm JD70-103 or JD70-107 Alternate 0/90 deg diamond configuration
TAC Runs 1.5? 72 <2 nA - 3.4 mm AMO (2x10-5)
All Non-production total 5.6 269 - - - - -