Senderovich (Talk | contribs) m (→Notes) |
|||
Line 23: | Line 23: | ||
* Latest news from SINMAT, as of June 20: | * Latest news from SINMAT, as of June 20: | ||
<blockquote> | <blockquote> | ||
− | We have solved the problems etching now. We are trying to | + | We have solved the problems etching now. We are trying to thin down. There was a problem with the etching tool. Now it is fixed. I hope to get it thinned in a week's time. |
</blockquote> | </blockquote> |
Revision as of 11:40, 25 June 2012
- Time: 11:30 EST
- Place: ESNET and EVO (with telephone bridge id 549 9207)
- Connecting: instructions are here
- Present: Michael D., Barry R., Dan S., Tim W., Alex S., Liping G., Yi Q., Curtis M., Richard J., Brendan P, Alex B., Fridah M., and Igor S.
Agenda
- Announcements
- Report from Glasgow group -- Ken
- Report from CUA group -- Franz, Alex
- Report from ASU group -- Mike
- Report from UNCW group -- Liping
- Discussion with accelerator group on beam parameters -- Alex
- Progress on UConn construction contract -- Alex
- June 8 -- Issue solicitation
- June 23 -- Receive proposals
- Update on diamond radiator fabrication -- Brendan
- Update on microscope construction -- James
- possible loan of DAq system with FADC to UConn
- possible swap of two SIPM's with Jlab (soon?)
Notes
- Latest news from SINMAT, as of June 20:
We have solved the problems etching now. We are trying to thin down. There was a problem with the etching tool. Now it is fixed. I hope to get it thinned in a week's time.