=Notes=
 +
 +
JLab: Tim, Simon, David, Carl, Eugene, Mark, John D., Dan, Elke, Claus<br>
 +
UConn: Richard<br>
 +
IUCF: Gerard<br>
 +
Curtis
 +
Christine
 +
 +
* JLab in a hiring freeze
 +
* next week mon to fri evms review, cost account managers
 +
physics is wed morning
 +
* proposal to drop meeting next week, agreed
 +
 +
==r&d contracts==
 +
 +
procurement
 +
2002-2007 contracts up status needs to be addressed
 +
iucf
 +
regina
 +
close and re-open new ones
 +
elke has list of all known contracts, excel spreadsheet will be sent around
 +
 +
===calorimeter===
 +
 +
zisis link to meeting page, minutes posted there
 +
tim will send something to the machine shop today
 +
 +
=detector updates=
 +
 +
==beamline and tagger==
 +
 +
design contract for tagger to procurement soon
 +
will be reviewed by acc division
 +
documents on the wiki are near up-to-date
 +
sampling of tagger interface drawing will be sent this week, tim
 +
 +
==solenoid==
 +
 +
coil 3 looks worse that we thought. completely open and replace some tubing, george. contract things to be sorted out
 +
started testing coils at jlab
 +
 +
===target===
 +
 +
tim meeting yesterday, reviewed tracking list, temporary solid target discussed for startup
 +
specification work to do reviewed
 +
racks for gas system, system itself
 +
alignment accuracies
 +
thermometry
 +
cryogenics: independent system or use magnet system
 +
 +
===start counter===
 +
 +
werner
 +
discussion started: geometry
 +
overall dimensions, stay-in zone
 +
target independent of start counter desired
 +
2004 geometry for counters itself still looks good with current rate estimates

Revision as of 11:31, 28 November 2007

Meeting Time and Place

  • Location:
  • ESNET: 8242553
  • Phone:
    • +1-800-377-8846 : US
    • +1-888-276-7715 : Canada
    • +1-302-709-8424 : International
    • Enter Code: 39527048#
  • Time: 10:00am EST

Agenda

  • Announcements
  • Reports from Technical Groups
  • Overview of on-going R&D contracts.
  • Detector Updates
    • Beamline & Tagger
    • Solenoid
    • Target
    • Start Counter
    • UPV
    • CDC (Status Report on the CDC_21_11_2007 CDC_28_11_2007 )
    • FDC
    • BCAL
    • TOF
    • FCAL
    • Electronics
    • Online
    • Offline
    • Monte Carlo
  • AOT

Meeting Notes

  • Announcements

The weekly Wednesday meeting for December 5 (next week) is cancelled. Jefferson Lab is now under a hiring freeze, because of the continuing resolution funding of the federal government. This does not affect the offers currently going out for the current position.

  • Reports from Technical Groups
  • Overview of on-going R&D contracts.
  • Detector Updates
  • Beamline & Tagger
  • Solenoid
  • Target
  • Start Counter
  • UPV
  • CDC (Status Report on the CDC_21_11_2007 CDC_28_11_2007 )
  • FDC
  • BCAL
  • TOF
  • FCAL
  • Electronics
  • Online
  • Offline
  • Monte Carlo
  • AOT

Notes

JLab: Tim, Simon, David, Carl, Eugene, Mark, John D., Dan, Elke, Claus
UConn: Richard
IUCF: Gerard
Curtis Christine

  • JLab in a hiring freeze
  • next week mon to fri evms review, cost account managers

physics is wed morning

  • proposal to drop meeting next week, agreed

r&d contracts

procurement 2002-2007 contracts up status needs to be addressed

iucf
regina

close and re-open new ones elke has list of all known contracts, excel spreadsheet will be sent around

calorimeter

zisis link to meeting page, minutes posted there tim will send something to the machine shop today

detector updates

beamline and tagger

design contract for tagger to procurement soon will be reviewed by acc division documents on the wiki are near up-to-date sampling of tagger interface drawing will be sent this week, tim

solenoid

coil 3 looks worse that we thought. completely open and replace some tubing, george. contract things to be sorted out started testing coils at jlab

target

tim meeting yesterday, reviewed tracking list, temporary solid target discussed for startup specification work to do reviewed racks for gas system, system itself alignment accuracies thermometry cryogenics: independent system or use magnet system

start counter

werner discussion started: geometry overall dimensions, stay-in zone target independent of start counter desired 2004 geometry for counters itself still looks good with current rate estimates