https://halldweb1.jlab.org/wiki/api.php?action=feedcontributions&user=Stjore&feedformat=atomGlueXWiki - User contributions [en]2024-03-28T23:34:01ZUser contributionsMediaWiki 1.24.1https://halldweb1.jlab.org/wiki/index.php?title=JEF_meeting,_March_22,_2024&diff=125198JEF meeting, March 22, 20242024-03-22T10:41:10Z<p>Stjore: /* Agenda */</p>
<hr />
<div>=Agenda=<br />
<br />
*'''Preparation of parts for ECAL''' -- Sasha <br />
** - signal cables - done<br />
** - signal patch panel [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/10_13_2023/signal_patch_panel.jpg ] - done<br />
** - HV short cables: received, checked, labeled (last week)<br />
** - HV long cable, 18 ready (out of 36) <br />
** - HV distribution boards: in preparation<br />
** - LV cables: 100 cables received, 640 cables in total<br />
** - LV distribution boards [https://halldweb.jlab.org/detectors/fcal2/cables/lv_distribution/lv_dist_board.jpg ]. Have to populate with connectors, and design a box around the PCB<br />
* '''Ongoing projects''' -- Sasha / Vlad / Hakob / Laveen<br />
** - Tested and labeled all HV cables ! and about 100 LV cables [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/03_21_2024/cable_labling.jpg]<br />
** - Bundling short cables (groups of 7, 7, and 6 cables)<br />
*** finished: LV - 13 layers, HV - 18 layers, signal - 9 layers (40 in total out of 120) [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/03_21_2024/cable_bundls1.jpg][https://halldweb.jlab.org/detectors/fcal2/installation/meetings/03_21_2024/cable_bundls2.jpg]<br />
* '''[[Testing of PMT dividers]]''' -- Sasha / Vlad / George<br />
** - Testing procedure [https://halldweb.jlab.org/detectors/fcal2/dividers/divider_test_guide.pptx]<br />
** - About 1420 dividers have been fabricated (Chris, Armen, Mindy)<br />
** - Started removing power regulators on the newly fabricated dividers<br />
** - George has tested 142 dividers (1063 have been tested in total) [https://halldweb.jlab.org/wiki/index.php/Final_test_of_dividers].<br />
** - Adding ECAL (and updating FCAL) translation table in the TT.DB (needed for EPICS scalers) <br />
* '''Installation of the FCAL2 detector & integration to GlueX''' -- Sasha / Vlad / Hakob / Laveen <br />
** Preparing safety documents. The following ePASes have been submitted and approved -- Sasha and Vlad<br />
*** Installation of the ECAL LMS <br />
*** Installation of cables and dividers, <br />
*** Beam tests with the PS test setup <br />
*** Preparing ECAL cables (EEL126)<br />
*** Fabrication of calorimeter prototypes (EEL126) <br />
*** Testing ECAL dividers (EEL118) (approved in January)<br />
** Installation of the LMS <br />
*** 1132 fibers have been installed [https://logbooks.jlab.org/entry/4270174]<br />
** Cable and divider installation [https://logbooks.jlab.org/entry/4249243][https://halldweb.jlab.org/detectors/fcal2/installation/meetings/02_16_2024/install_cable1.jpg][https://halldweb.jlab.org/detectors/fcal2/installation/meetings/02_16_2024/install_cable2.jpg]<br />
** Power installation on the platform has been completed [https://logbooks.jlab.org/entry/4262698]<br />
** [https://halldweb.jlab.org/wiki/index.php/FCAL_Installation Detector installation page]<br />
*** (links from the previous meetings [https://logbooks.jlab.org/book/halld][https://halldweb.jlab.org/detectors/fcal2/installation/photos/install_fcal/students_detector1.jpg][https://halldweb.jlab.org/detectors/fcal2/installation/photos/install_fcal/students_detector.jpg])<br />
<br />
*'''Analysis/Simulation'''<br />
** Generated bggen eta->pi0gg events with JEF geometry for background studies [https://halldweb.jlab.org/DocDB/0064/006427/001/JEF%20Simulations%20v2.3.pdf] -- Stjepan</div>Stjorehttps://halldweb1.jlab.org/wiki/index.php?title=JEF_meeting,_March_22,_2024&diff=125197JEF meeting, March 22, 20242024-03-22T10:40:41Z<p>Stjore: /* Agenda */</p>
<hr />
<div>=Agenda=<br />
<br />
*'''Preparation of parts for ECAL''' -- Sasha <br />
** - signal cables - done<br />
** - signal patch panel [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/10_13_2023/signal_patch_panel.jpg ] - done<br />
** - HV short cables: received, checked, labeled (last week)<br />
** - HV long cable, 18 ready (out of 36) <br />
** - HV distribution boards: in preparation<br />
** - LV cables: 100 cables received, 640 cables in total<br />
** - LV distribution boards [https://halldweb.jlab.org/detectors/fcal2/cables/lv_distribution/lv_dist_board.jpg ]. Have to populate with connectors, and design a box around the PCB<br />
* '''Ongoing projects''' -- Sasha / Vlad / Hakob / Laveen<br />
** - Tested and labeled all HV cables ! and about 100 LV cables [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/03_21_2024/cable_labling.jpg]<br />
** - Bundling short cables (groups of 7, 7, and 6 cables)<br />
*** finished: LV - 13 layers, HV - 18 layers, signal - 9 layers (40 in total out of 120) [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/03_21_2024/cable_bundls1.jpg][https://halldweb.jlab.org/detectors/fcal2/installation/meetings/03_21_2024/cable_bundls2.jpg]<br />
* '''[[Testing of PMT dividers]]''' -- Sasha / Vlad / George<br />
** - Testing procedure [https://halldweb.jlab.org/detectors/fcal2/dividers/divider_test_guide.pptx]<br />
** - About 1420 dividers have been fabricated (Chris, Armen, Mindy)<br />
** - Started removing power regulators on the newly fabricated dividers<br />
** - George has tested 142 dividers (1063 have been tested in total) [https://halldweb.jlab.org/wiki/index.php/Final_test_of_dividers].<br />
** - Adding ECAL (and updating FCAL) translation table in the TT.DB (needed for EPICS scalers) <br />
* '''Installation of the FCAL2 detector & integration to GlueX''' -- Sasha / Vlad / Hakob / Laveen <br />
** Preparing safety documents. The following ePASes have been submitted and approved -- Sasha and Vlad<br />
*** Installation of the ECAL LMS <br />
*** Installation of cables and dividers, <br />
*** Beam tests with the PS test setup <br />
*** Preparing ECAL cables (EEL126)<br />
*** Fabrication of calorimeter prototypes (EEL126) <br />
*** Testing ECAL dividers (EEL118) (approved in January)<br />
** Installation of the LMS <br />
*** 1132 fibers have been installed [https://logbooks.jlab.org/entry/4270174]<br />
** Cable and divider installation [https://logbooks.jlab.org/entry/4249243][https://halldweb.jlab.org/detectors/fcal2/installation/meetings/02_16_2024/install_cable1.jpg][https://halldweb.jlab.org/detectors/fcal2/installation/meetings/02_16_2024/install_cable2.jpg]<br />
** Power installation on the platform has been completed [https://logbooks.jlab.org/entry/4262698]<br />
** [https://halldweb.jlab.org/wiki/index.php/FCAL_Installation Detector installation page]<br />
*** (links from the previous meetings [https://logbooks.jlab.org/book/halld][https://halldweb.jlab.org/detectors/fcal2/installation/photos/install_fcal/students_detector1.jpg][https://halldweb.jlab.org/detectors/fcal2/installation/photos/install_fcal/students_detector.jpg])<br />
<br />
*'''Analysis/Simulation'''<br />
** Generated bggen eta->pi0gg events with JEF geometry for background studies [https://halldweb.jlab.org/DocDB/0064/006427/001/JEF%20Simulations%20v2.3.pdf]</div>Stjorehttps://halldweb1.jlab.org/wiki/index.php?title=JEF_meeting,_February_2,_2024&diff=124554JEF meeting, February 2, 20242024-02-02T15:53:37Z<p>Stjore: /* Agenda */</p>
<hr />
<div>Meeting time and location:<br />
*9:30 am EST (JLab time) remote only<br />
* [https://halldweb.jlab.org/wiki-private/index.php/JEF_Weekly_Meeting#Connection_information Connection information]<br />
<br />
=Agenda=<br />
<br />
*'''Preparation of parts for ECAL''' -- Sasha <br />
** - signal cables - done<br />
** - signal patch panel [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/10_13_2023/signal_patch_panel.jpg ] - done<br />
** - HV cables: received 1280 in total<br />
** - HV distribution boards: in preparation<br />
** - LV cables: 150 cables received <br />
** - LV distribution boards. Received 4 boards, performed initial cehck, need to solder connectors [https://halldweb.jlab.org/detectors/fcal2/cables/lv_distribution/lv_dist_board.jpg ]<br />
** - Optical fibers and parts for the trigger/DAQ have been ordered<br />
* '''Ongoing projects''' -- Sasha, all<br />
** - Testing and labeling cables, 100 short LV cables tested and labeled during this week.<br />
** - Prepare modules for the TAC and prototypes (using crystals with some imperfections)<br />
*** 26 modules for TAC [https://halldweb.jlab.org/detectors/fcal2/modules_for_prototype/tac_mod.jpg] and 35 modules [https://halldweb.jlab.org/detectors/fcal2/modules_for_prototype/prot_mod.jpg] for the beam tests are ready<br />
** - Preparation of the LMS <br />
*** - Need to glue Al flange to the optical fiber<br />
*** - Ready for installation [https://halldweb.jlab.org/detectors/fcal2/lms/installation] <br />
** - Radiation tests of the PMT active base [https://halldweb.jlab.org/wiki/index.php/Active_Base_Radiation_Tests]<br />
*** Finished tests, working on the tech note<br />
** - [https://halldweb.jlab.org/detectors/AL/HallD_Racks Inventory database and GUI for installed electronics ]<br />
** - [https://halldweb.jlab.org/detectors/fcal2/installation/students_2023/list_of_students_2023.xlsx Summer Students (2023) ]<br />
* '''[[Testing of PMT dividers]]''' -- Sasha / Vlad / Aoran <br />
** - Testing procedure [https://halldweb.jlab.org/detectors/fcal2/dividers/divider_test_guide.pptx]<br />
** - Tested 637 divider (all fabricated dividers) [https://halldweb.jlab.org/wiki/index.php/Final_test_of_dividers]. No dividers produced during this week.<br />
** - Spare PMTs, have about 20, likely need more for the future (order 30 more )?<br />
* '''Installation of the FCAL2 detector & integration to GlueX''' -- Sasha / Vlad / Hakob<br />
** Detector installation [https://logbooks.jlab.org/book/halld][https://halldweb.jlab.org/detectors/fcal2/installation/photos/install_fcal/students_detector1.jpg][https://halldweb.jlab.org/detectors/fcal2/installation/photos/install_fcal/students_detector.jpg]<br />
** Installation of the LMS <br />
*** 143 fibers installed during this week (some delays with trainings and safety docs) [https://logbooks.jlab.org/entry/4246934] [https://logbooks.jlab.org/entry/4243052]<br />
*** Had to obtain trainings for operating scissor lift (operation without training violates safety rules) (revealed some issues with the lift when inspected by Joe Thomas)<br />
** Cable and divider installation [https://logbooks.jlab.org/entry/4245946]<br />
*** Bundled and installed signal, HV, and LV cables on the first layer [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/02_02_2024/inst_div_02_02.jpg][https://halldweb.jlab.org/detectors/fcal2/installation/meetings/02_02_2024/cable_instal.jpg][https://halldweb.jlab.org/detectors/fcal2/installation/meetings/02_02_2024/cable_instal1.jpg]<br />
** Still no power on the ECAL platform (expect delay with the development of the trigger/DAQ)<br />
** [https://halldweb.jlab.org/wiki/index.php/FCAL_Installation Detector installation page]<br />
* '''Simulations''' -- Simon / Stjepan<br />
** pi0gg channel simulations and analysis done with genEtaRegge and analyzed with FSRoot for the JEF FCAL2 geometry [https://halldweb.jlab.org/DocDB/0063/006339/001/JEF%20Simulations%20v2%20Complete.pdf]</div>Stjorehttps://halldweb1.jlab.org/wiki/index.php?title=JEF_meeting,_February_2,_2024&diff=124553JEF meeting, February 2, 20242024-02-02T15:53:19Z<p>Stjore: /* Agenda */</p>
<hr />
<div>Meeting time and location:<br />
*9:30 am EST (JLab time) remote only<br />
* [https://halldweb.jlab.org/wiki-private/index.php/JEF_Weekly_Meeting#Connection_information Connection information]<br />
<br />
=Agenda=<br />
<br />
*'''Preparation of parts for ECAL''' -- Sasha <br />
** - signal cables - done<br />
** - signal patch panel [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/10_13_2023/signal_patch_panel.jpg ] - done<br />
** - HV cables: received 1280 in total<br />
** - HV distribution boards: in preparation<br />
** - LV cables: 150 cables received <br />
** - LV distribution boards. Received 4 boards, performed initial cehck, need to solder connectors [https://halldweb.jlab.org/detectors/fcal2/cables/lv_distribution/lv_dist_board.jpg ]<br />
** - Optical fibers and parts for the trigger/DAQ have been ordered<br />
* '''Ongoing projects''' -- Sasha, all<br />
** - Testing and labeling cables, 100 short LV cables tested and labeled during this week.<br />
** - Prepare modules for the TAC and prototypes (using crystals with some imperfections)<br />
*** 26 modules for TAC [https://halldweb.jlab.org/detectors/fcal2/modules_for_prototype/tac_mod.jpg] and 35 modules [https://halldweb.jlab.org/detectors/fcal2/modules_for_prototype/prot_mod.jpg] for the beam tests are ready<br />
** - Preparation of the LMS <br />
*** - Need to glue Al flange to the optical fiber<br />
*** - Ready for installation [https://halldweb.jlab.org/detectors/fcal2/lms/installation] <br />
** - Radiation tests of the PMT active base [https://halldweb.jlab.org/wiki/index.php/Active_Base_Radiation_Tests]<br />
*** Finished tests, working on the tech note<br />
** - [https://halldweb.jlab.org/detectors/AL/HallD_Racks Inventory database and GUI for installed electronics ]<br />
** - [https://halldweb.jlab.org/detectors/fcal2/installation/students_2023/list_of_students_2023.xlsx Summer Students (2023) ]<br />
* '''[[Testing of PMT dividers]]''' -- Sasha / Vlad / Aoran <br />
** - Testing procedure [https://halldweb.jlab.org/detectors/fcal2/dividers/divider_test_guide.pptx]<br />
** - Tested 637 divider (all fabricated dividers) [https://halldweb.jlab.org/wiki/index.php/Final_test_of_dividers]. No dividers produced during this week.<br />
** - Spare PMTs, have about 20, likely need more for the future (order 30 more )?<br />
* '''Installation of the FCAL2 detector & integration to GlueX''' -- Sasha / Vlad / Hakob<br />
** Detector installation [https://logbooks.jlab.org/book/halld][https://halldweb.jlab.org/detectors/fcal2/installation/photos/install_fcal/students_detector1.jpg][https://halldweb.jlab.org/detectors/fcal2/installation/photos/install_fcal/students_detector.jpg]<br />
** Installation of the LMS <br />
*** 143 fibers installed during this week (some delays with trainings and safety docs) [https://logbooks.jlab.org/entry/4246934] [https://logbooks.jlab.org/entry/4243052]<br />
*** Had to obtain trainings for operating scissor lift (operation without training violates safety rules) (revealed some issues with the lift when inspected by Joe Thomas)<br />
** Cable and divider installation [https://logbooks.jlab.org/entry/4245946]<br />
*** Bundled and installed signal, HV, and LV cables on the first layer [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/02_02_2024/inst_div_02_02.jpg][https://halldweb.jlab.org/detectors/fcal2/installation/meetings/02_02_2024/cable_instal.jpg][https://halldweb.jlab.org/detectors/fcal2/installation/meetings/02_02_2024/cable_instal1.jpg]<br />
** Still no power on the ECAL platform (expect delay with the development of the trigger/DAQ)<br />
** [https://halldweb.jlab.org/wiki/index.php/FCAL_Installation Detector installation page]<br />
* '''[Simulations]''' -- Simon / Stjepan<br />
** pi0gg channel simulations and analysis done with genEtaRegge and analyzed with FSRoot for the JEF FCAL2 geometry [https://halldweb.jlab.org/DocDB/0063/006339/001/JEF%20Simulations%20v2%20Complete.pdf]</div>Stjorehttps://halldweb1.jlab.org/wiki/index.php?title=May_22,_2023_Calorimeter&diff=121057May 22, 2023 Calorimeter2023-05-22T16:09:55Z<p>Stjore: /* Minutes */</p>
<hr />
<div><font color=red>Meeting Day/Time: MONDAY at 11:00 a.m. JLab time (monthly frequency during the long shutdown)</font>''<br><br />
<br />
=Connection instructions=<br />
<br />
[https://halldweb.jlab.org/wiki-private/index.php/Connect_to_ZoomGov_Meetings Connect to ZoomGov Meetings]<br />
<br />
= References =<br />
<br />
# FCAL [https://logbooks.jlab.org/book/hdfcal HDFCAL log book]<br />
# ECAL [https://logbooks.jlab.org/book/hdfcal2 HDECAL log book]<br />
# BCAL [https://logbooks.jlab.org/book/hdbcal HDBCAL log book]<br />
# CCAL [https://logbooks.jlab.org/book/hdccal HDCCAL log book]<br />
# Calibrations: [https://halldweb.jlab.org/wiki/index.php/2020_Data_Production 2020 Data Production]; [https://halldweb.jlab.org/wiki/index.php/RunPeriod-2019-11_Validation#Monitoring_Launch_Checks RunPeriod-2019-11 Validation]; [https://halldweb.jlab.org/wiki/index.php/Offline_Monitoring_Data_Validation Offline Monitoring Data Validation]<br />
# [https://halldweb.jlab.org/wiki-private/index.php/2020_Analysis_Task_Forces#Photon_Reconstruction_Systematics_Task_Force Photon Reconstruction Task Force]<br />
# [[BCAL calibration links, 2020, PrimEx, SRC]]<br />
<br />
= Tentative Agenda =<br />
<br />
# Announcements, Regina will not calibrate BCAL for CPP/NPP & PrimEx data sets<br />
# How to calibrate BCAL? (Karthik & Stjepan)<br />
# Replacement candidates?<br />
<br />
= Minutes =<br />
<br />
Slides showing the calibration process details with estimated time for each step, along with the current status of PrimEx 2022 calibration (Stjepan) [https://halldweb.jlab.org/doc-private/DocDB/ShowDocument?docid=6032]</div>Stjorehttps://halldweb1.jlab.org/wiki/index.php?title=March_15,_2023_Calorimeter&diff=120286March 15, 2023 Calorimeter2023-03-15T15:00:23Z<p>Stjore: /* Tentative Agenda */</p>
<hr />
<div><font color=red>Meeting Day/Time: every other WEDNESDAY at 11:00 a.m. JLab time</font>''<br><br />
<br />
=Connection instructions=<br />
<div class="toccolours mw-collapsible mw-collapsed"><br />
Use ZoomGov: https://jlab-org.zoomgov.com/j/1608552106?pwd=UE1nZFIzUUZHVjJEVGJXTGdUYTV3UT09. <br><br />
Our meeting ID number is '''160 855 2106'''. Click "Expand" for more details.<br />
<div class="mw-collapsible-content"><br />
* Meeting ID: 160 855 2106 Passcode: 944454<br />
* One tap mobile<br />
+16692545252,,1608552106# US (San Jose)<br />
+16468287666,,1608552106# US (New York)<br />
* Dial by your location<br />
+1 669 254 5252 US (San Jose)<br />
+1 646 828 7666 US (New York)<br />
+1 551 285 1373 US<br />
+1 669 216 1590 US (San Jose)<br />
833 568 8864 US Toll-free<br />
* Meeting ID: 160 855 2106<br />
* Find your local number: https://jlab-org.zoomgov.com/u/acAwPdiE89<br />
* Join by SIP 1608552106@sip.zoomgov.com<br />
* Join by H.323<br />
161.199.138.10 (US West)<br />
161.199.136.10 (US East)<br />
Meeting ID: 160 855 2106<br />
Passcode: 944454<br />
</div><br />
</div><br />
<br />
= References =<br />
<br />
# FCAL [https://logbooks.jlab.org/book/hdfcal HDFCAL log book]<br />
# BCAL [https://logbooks.jlab.org/book/hdbcal HDBCAL log book]<br />
# CCAL [https://logbooks.jlab.org/book/hdccal HDCCAL log book]<br />
# Calibrations: [https://halldweb.jlab.org/wiki/index.php/2020_Data_Production 2020 Data Production]; [https://halldweb.jlab.org/wiki/index.php/RunPeriod-2019-11_Validation#Monitoring_Launch_Checks RunPeriod-2019-11 Validation]; [https://halldweb.jlab.org/wiki/index.php/Offline_Monitoring_Data_Validation Offline Monitoring Data Validation]<br />
# [https://halldweb.jlab.org/wiki-private/index.php/2020_Analysis_Task_Forces#Photon_Reconstruction_Systematics_Task_Force Photon Reconstruction Task Force]<br />
# [[BCAL calibration links, 2020, PrimEx, SRC]]<br />
<br />
= Goals for Calorimetry Group =<br />
<br />
# Determine preliminary photon reconstruction efficiencies as a function of E, phi and theta in data and simulation with a point-to-point precision of at least 5%.<br />
# Measure systematics of pi0/eta mass calibration as a function of detector position to a precision of at least 5 MeV.<br />
# Demonstrate agreement of photon resolution between data and simulation as a function of E, phi and theta to within 5%.<br />
# Demonstrate agreement of photon reconstruction efficiency between data and simulation as a function of E, phi and theta to within 5%.<br />
<br />
= Action Items =<br />
<br />
# [[Short term CALWG Items]]<br />
# [[Long term items]]<br />
# [https://halldweb.jlab.org/wiki-private/index.php/2018_Work_Packages#Calorimetry Calorimeter work packages]<br />
# AI - BCAL Monitoring:<br />
## [https://halldweb.jlab.org/hydra/HydraRun.html Hydra Real-Time Dashboard]<br />
## [https://halldweb.jlab.org/hydra/HydraLog.html Hydra 24-hr Monitoring Logs]<br />
<br />
= Tentative Agenda =<br />
<br />
# Announcements<br />
# Past Meeting Minutes<br />
# Review Action Items<br />
# Run Operations<br />
## FCAL/FCAL2<br />
## BCAL<br />
# Calibration<br />
## BCAL: Stjepan - PrimEx 2022 gain calibration will start soon, most likely starting from the 2021 SRC carbon target gain ratios <br />
# Monitoring<br />
## BCAL: Varun- LED monitoring Update. Modules 42,43 look normal so far after the ISEG module changing incident see [https://logbooks.jlab.org/entry/4149694 elog 4149694]<br />
# Reconstruction<br />
# Simulations<br />
# Any other business<br />
## Mini BCAL beam test update<br />
<br />
= Minutes =<br />
''Attendees: ''</div>Stjorehttps://halldweb1.jlab.org/wiki/index.php?title=August_3,_2022_Calorimeter&diff=114922August 3, 2022 Calorimeter2022-08-03T15:11:53Z<p>Stjore: /* Tentative Agenda */</p>
<hr />
<div><font color=red>Meeting Day/Time: every other WEDNESDAY at 11:00 a.m. JLab time</font>''<br><br />
<br />
=Connection instructions=<br />
<div class="toccolours mw-collapsible mw-collapsed"><br />
Use ZoomGov: https://jlab-org.zoomgov.com/j/1608552106?pwd=UE1nZFIzUUZHVjJEVGJXTGdUYTV3UT09. <br><br />
Our meeting ID number is '''160 855 2106'''. Click "Expand" for more details.<br />
<div class="mw-collapsible-content"><br />
* Meeting ID: 160 855 2106 Passcode: 944454<br />
* One tap mobile<br />
+16692545252,,1608552106# US (San Jose)<br />
+16468287666,,1608552106# US (New York)<br />
* Dial by your location<br />
+1 669 254 5252 US (San Jose)<br />
+1 646 828 7666 US (New York)<br />
+1 551 285 1373 US<br />
+1 669 216 1590 US (San Jose)<br />
833 568 8864 US Toll-free<br />
* Meeting ID: 160 855 2106<br />
* Find your local number: https://jlab-org.zoomgov.com/u/acAwPdiE89<br />
* Join by SIP 1608552106@sip.zoomgov.com<br />
* Join by H.323<br />
161.199.138.10 (US West)<br />
161.199.136.10 (US East)<br />
Meeting ID: 160 855 2106<br />
Passcode: 944454<br />
</div><br />
</div><br />
<br />
= References =<br />
<br />
# FCAL [https://logbooks.jlab.org/book/hdfcal HDFCAL log book]<br />
# BCAL [https://logbooks.jlab.org/book/hdbcal HDBCAL log book]<br />
# CCAL [https://logbooks.jlab.org/book/hdccal HDCCAL log book]<br />
# Calibrations: [https://halldweb.jlab.org/wiki/index.php/2020_Data_Production 2020 Data Production]; [https://halldweb.jlab.org/wiki/index.php/RunPeriod-2019-11_Validation#Monitoring_Launch_Checks RunPeriod-2019-11 Validation]; [https://halldweb.jlab.org/wiki/index.php/Offline_Monitoring_Data_Validation Offline Monitoring Data Validation]<br />
# [https://halldweb.jlab.org/wiki-private/index.php/2020_Analysis_Task_Forces#Photon_Reconstruction_Systematics_Task_Force Photon Reconstruction Task Force]<br />
# [[BCAL calibration links, 2020, PrimEx, SRC]]<br />
<br />
= Goals for Calorimetry Group =<br />
<br />
# Determine preliminary photon reconstruction efficiencies as a function of E, phi and theta in data and simulation with a point-to-point precision of at least 5%.<br />
# Measure systematics of pi0/eta mass calibration as a function of detector position to a precision of at least 5 MeV.<br />
# Demonstrate agreement of photon reconstruction efficiency and resolution between data and simulation as a function of E, phi and theta to within 5%.<br />
<br />
= Action Items =<br />
<br />
# [[Short term CALWG Items]]<br />
# [[Long term items]]<br />
# [https://halldweb.jlab.org/wiki-private/index.php/2018_Work_Packages#Calorimetry Calorimeter work packages]<br />
# AI - BCAL Monitoring:<br />
## [https://halldweb.jlab.org/hydra/HydraRun.html Hydra Real-Time Dashboard]<br />
## [https://halldweb.jlab.org/hydra/HydraLog.html Hydra 24-hr Monitoring Logs]<br />
<br />
= Tentative Agenda =<br />
<br />
# Announcements<br />
# Past Meeting Minutes<br />
# Shutdown tasks<br />
## Review Action Items<br />
# Run Operations<br />
## FCAL<br />
## BCAL<br />
## CCAL<br />
# Calibration<br />
##Stjepan: Brief update on the status of the PrimEx BCAL calibration for the magnetic field off targets. [https://halldweb.jlab.org/DocDB/0055/005530/001/pi0gainmatrixPrimExIter17OFF3%5B1025%5D.pdf]<br />
# Monitoring<br />
## BCAL (offline)<br />
###Tolga: Brief update on adding phi to Hadronic Efficiencies scripts. [https://halldweb.jlab.org/DocDB/0056/005699/001/ver07mon-20220803.pdf]<br />
## FCAL (offline)<br />
## CCAL (offline)<br />
# Reconstruction<br />
# Simulations<br />
# Any other business</div>Stjorehttps://halldweb1.jlab.org/wiki/index.php?title=August_3,_2022_Calorimeter&diff=114921August 3, 2022 Calorimeter2022-08-03T15:11:43Z<p>Stjore: /* Tentative Agenda */</p>
<hr />
<div><font color=red>Meeting Day/Time: every other WEDNESDAY at 11:00 a.m. JLab time</font>''<br><br />
<br />
=Connection instructions=<br />
<div class="toccolours mw-collapsible mw-collapsed"><br />
Use ZoomGov: https://jlab-org.zoomgov.com/j/1608552106?pwd=UE1nZFIzUUZHVjJEVGJXTGdUYTV3UT09. <br><br />
Our meeting ID number is '''160 855 2106'''. Click "Expand" for more details.<br />
<div class="mw-collapsible-content"><br />
* Meeting ID: 160 855 2106 Passcode: 944454<br />
* One tap mobile<br />
+16692545252,,1608552106# US (San Jose)<br />
+16468287666,,1608552106# US (New York)<br />
* Dial by your location<br />
+1 669 254 5252 US (San Jose)<br />
+1 646 828 7666 US (New York)<br />
+1 551 285 1373 US<br />
+1 669 216 1590 US (San Jose)<br />
833 568 8864 US Toll-free<br />
* Meeting ID: 160 855 2106<br />
* Find your local number: https://jlab-org.zoomgov.com/u/acAwPdiE89<br />
* Join by SIP 1608552106@sip.zoomgov.com<br />
* Join by H.323<br />
161.199.138.10 (US West)<br />
161.199.136.10 (US East)<br />
Meeting ID: 160 855 2106<br />
Passcode: 944454<br />
</div><br />
</div><br />
<br />
= References =<br />
<br />
# FCAL [https://logbooks.jlab.org/book/hdfcal HDFCAL log book]<br />
# BCAL [https://logbooks.jlab.org/book/hdbcal HDBCAL log book]<br />
# CCAL [https://logbooks.jlab.org/book/hdccal HDCCAL log book]<br />
# Calibrations: [https://halldweb.jlab.org/wiki/index.php/2020_Data_Production 2020 Data Production]; [https://halldweb.jlab.org/wiki/index.php/RunPeriod-2019-11_Validation#Monitoring_Launch_Checks RunPeriod-2019-11 Validation]; [https://halldweb.jlab.org/wiki/index.php/Offline_Monitoring_Data_Validation Offline Monitoring Data Validation]<br />
# [https://halldweb.jlab.org/wiki-private/index.php/2020_Analysis_Task_Forces#Photon_Reconstruction_Systematics_Task_Force Photon Reconstruction Task Force]<br />
# [[BCAL calibration links, 2020, PrimEx, SRC]]<br />
<br />
= Goals for Calorimetry Group =<br />
<br />
# Determine preliminary photon reconstruction efficiencies as a function of E, phi and theta in data and simulation with a point-to-point precision of at least 5%.<br />
# Measure systematics of pi0/eta mass calibration as a function of detector position to a precision of at least 5 MeV.<br />
# Demonstrate agreement of photon reconstruction efficiency and resolution between data and simulation as a function of E, phi and theta to within 5%.<br />
<br />
= Action Items =<br />
<br />
# [[Short term CALWG Items]]<br />
# [[Long term items]]<br />
# [https://halldweb.jlab.org/wiki-private/index.php/2018_Work_Packages#Calorimetry Calorimeter work packages]<br />
# AI - BCAL Monitoring:<br />
## [https://halldweb.jlab.org/hydra/HydraRun.html Hydra Real-Time Dashboard]<br />
## [https://halldweb.jlab.org/hydra/HydraLog.html Hydra 24-hr Monitoring Logs]<br />
<br />
= Tentative Agenda =<br />
<br />
# Announcements<br />
# Past Meeting Minutes<br />
# Shutdown tasks<br />
## Review Action Items<br />
# Run Operations<br />
## FCAL<br />
## BCAL<br />
## CCAL<br />
# Calibration<br />
###Stjepan: Brief update on the status of the PrimEx BCAL calibration for the magnetic field off targets. [https://halldweb.jlab.org/DocDB/0055/005530/001/pi0gainmatrixPrimExIter17OFF3%5B1025%5D.pdf]<br />
# Monitoring<br />
## BCAL (offline)<br />
###Tolga: Brief update on adding phi to Hadronic Efficiencies scripts. [https://halldweb.jlab.org/DocDB/0056/005699/001/ver07mon-20220803.pdf]<br />
## FCAL (offline)<br />
## CCAL (offline)<br />
# Reconstruction<br />
# Simulations<br />
# Any other business</div>Stjorehttps://halldweb1.jlab.org/wiki/index.php?title=June_22,_2022_Calorimeter&diff=113647June 22, 2022 Calorimeter2022-06-22T15:08:57Z<p>Stjore: /* Tentative Agenda */</p>
<hr />
<div><font color=red>Meeting Day/Time: every other WEDNESDAY at 11:00 a.m. JLab time</font>''<br><br />
<br />
=Connection instructions=<br />
<div class="toccolours mw-collapsible mw-collapsed"><br />
Use ZoomGov: https://jlab-org.zoomgov.com/j/1608552106?pwd=UE1nZFIzUUZHVjJEVGJXTGdUYTV3UT09. <br><br />
Our meeting ID number is '''160 855 2106'''. Click "Expand" for more details.<br />
<div class="mw-collapsible-content"><br />
* Meeting ID: 160 855 2106 Passcode: 944454<br />
* One tap mobile<br />
+16692545252,,1608552106# US (San Jose)<br />
+16468287666,,1608552106# US (New York)<br />
* Dial by your location<br />
+1 669 254 5252 US (San Jose)<br />
+1 646 828 7666 US (New York)<br />
+1 551 285 1373 US<br />
+1 669 216 1590 US (San Jose)<br />
833 568 8864 US Toll-free<br />
* Meeting ID: 160 855 2106<br />
* Find your local number: https://jlab-org.zoomgov.com/u/acAwPdiE89<br />
* Join by SIP 1608552106@sip.zoomgov.com<br />
* Join by H.323<br />
161.199.138.10 (US West)<br />
161.199.136.10 (US East)<br />
Meeting ID: 160 855 2106<br />
Passcode: 944454<br />
</div><br />
</div><br />
<br />
= References =<br />
<br />
# FCAL [https://logbooks.jlab.org/book/hdfcal HDFCAL log book]<br />
# BCAL [https://logbooks.jlab.org/book/hdbcal HDBCAL log book]<br />
# CCAL [https://logbooks.jlab.org/book/hdccal HDCCAL log book]<br />
# Calibrations: [https://halldweb.jlab.org/wiki/index.php/2020_Data_Production 2020 Data Production]; [https://halldweb.jlab.org/wiki/index.php/RunPeriod-2019-11_Validation#Monitoring_Launch_Checks RunPeriod-2019-11 Validation]; [https://halldweb.jlab.org/wiki/index.php/Offline_Monitoring_Data_Validation Offline Monitoring Data Validation]<br />
# [https://halldweb.jlab.org/wiki-private/index.php/2020_Analysis_Task_Forces#Photon_Reconstruction_Systematics_Task_Force Photon Reconstruction Task Force]<br />
# [[BCAL calibration links, 2020, PrimEx, SRC]]<br />
<br />
= Goals for Calorimetry Group =<br />
<br />
# Determine preliminary photon reconstruction efficiencies as a function of E, phi and theta in data and simulation with a point-to-point precision of at least 5%.<br />
# Measure systematics of pi0/eta mass calibration as a function of detector position to a precision of at least 5 MeV.<br />
# Demonstrate agreement of photon reconstruction efficiency and resolution between data and simulation as a function of E, phi and theta to within 5%.<br />
<br />
= Action Items =<br />
<br />
# [[Short term CALWG Items]]<br />
# [[Long term items]]<br />
# [https://halldweb.jlab.org/wiki-private/index.php/2018_Work_Packages#Calorimetry Calorimeter work packages]<br />
# AI - BCAL Monitoring:<br />
## [https://halldweb.jlab.org/hydra/HydraRun.html Hydra Real-Time Dashboard]<br />
## [https://halldweb.jlab.org/hydra/HydraLog.html Hydra 24-hr Monitoring Logs]<br />
<br />
= Tentative Agenda =<br />
<br />
# Announcements<br />
# Past Meeting Minutes<br />
# Shutdown tasks<br />
## Review Action Items<br />
# Run Operations<br />
## [https://halldweb.jlab.org/wiki/index.php/FCAL FCAL] under FCAL calibration -> [https://halldweb.jlab.org/wiki/index.php/CPP_FCAL_time/energy_calibrations CPP FCAL time/energy calibrations] under <br />
### [https://halldweb.jlab.org/primexd/pb_cpp/ Gain matching calibration plots]<br />
### Timing calibration<br />
## BCAL<br />
## CCAL<br />
# Calibration<br />
#* [https://halldweb.jlab.org/wiki/index.php/File:InnerBlocks_30730-20220425.png Revisiting calibration of GlueX-I data]<br />
### Update on the status of the SRC and PrimEx BCAL calibrations (Stjepan) [https://halldweb.jlab.org/DocDB/0056/005663/001/Spring_Summer%202022%20Pi0%20BCAL%20Gain%20Callibration.pdf]<br />
# Monitoring<br />
## BCAL LED<br />
### Update-cpp (Varun)[https://halldweb.jlab.org/wiki/images/f/f1/BCAL_LED_monitoring_update.pdf]<br />
## BCAL (offline) <br />
###Brief update, Hadronic Efficiencies plots for Version 7 Monitoring, Tolga [https://halldweb.jlab.org/DocDB/0056/005662/001/CALWg-2020622.pdf]<br />
## FCAL (offline)<br />
### FCAL Timing Resolution (Kevin)[https://halldweb.jlab.org/DocDB/0056/005660/002/FCAL.pdf]<br />
## CCAL (offline)<br />
# Reconstruction<br />
##BCAL efficiency: Churamani [https://halldweb.jlab.org/DocDB/0056/005661/001/bcal_eff_TnP_june2022.pdf]<br />
# Simulations<br />
# Any other business<br />
<br />
= Minutes =<br />
''Attendees:''</div>Stjorehttps://halldweb1.jlab.org/wiki/index.php?title=March_16,_2022_Calorimeter&diff=111715March 16, 2022 Calorimeter2022-03-17T21:00:03Z<p>Stjore: /* Minutes */</p>
<hr />
<div><font color=red>Meeting Day/Time: every other WEDNESDAY at 11:00 a.m. JLab time</font>''<br><br />
<br />
=Connection instructions=<br />
<div class="toccolours mw-collapsible mw-collapsed"><br />
Use ZoomGov: https://jlab-org.zoomgov.com/j/1608552106?pwd=UE1nZFIzUUZHVjJEVGJXTGdUYTV3UT09. <br><br />
Our meeting ID number is '''160 855 2106'''. Click "Expand" for more details.<br />
<div class="mw-collapsible-content"><br />
* Meeting ID: 160 855 2106 Passcode: 944454<br />
* One tap mobile<br />
+16692545252,,1608552106# US (San Jose)<br />
+16468287666,,1608552106# US (New York)<br />
* Dial by your location<br />
+1 669 254 5252 US (San Jose)<br />
+1 646 828 7666 US (New York)<br />
+1 551 285 1373 US<br />
+1 669 216 1590 US (San Jose)<br />
833 568 8864 US Toll-free<br />
* Meeting ID: 160 855 2106<br />
* Find your local number: https://jlab-org.zoomgov.com/u/acAwPdiE89<br />
* Join by SIP 1608552106@sip.zoomgov.com<br />
* Join by H.323<br />
161.199.138.10 (US West)<br />
161.199.136.10 (US East)<br />
Meeting ID: 160 855 2106<br />
Passcode: 944454<br />
</div><br />
</div><br />
<br />
= References =<br />
<br />
# FCAL [https://logbooks.jlab.org/book/hdfcal HDFCAL log book]<br />
# BCAL [https://logbooks.jlab.org/book/hdbcal HDBCAL log book]<br />
# CCAL [https://logbooks.jlab.org/book/hdccal HDCCAL log book]<br />
# Calibrations: [https://halldweb.jlab.org/wiki/index.php/2020_Data_Production 2020 Data Production]; [https://halldweb.jlab.org/wiki/index.php/RunPeriod-2019-11_Validation#Monitoring_Launch_Checks RunPeriod-2019-11 Validation]; [https://halldweb.jlab.org/wiki/index.php/Offline_Monitoring_Data_Validation Offline Monitoring Data Validation]<br />
# [https://halldweb.jlab.org/wiki-private/index.php/2020_Analysis_Task_Forces#Photon_Reconstruction_Systematics_Task_Force Photon Reconstruction Task Force]<br />
# [[BCAL calibration links, 2020, PrimEx, SRC]]<br />
<br />
= Goals for Calorimetry Group =<br />
<br />
# Determine preliminary photon reconstruction efficiencies as a function of E, phi and theta in data and simulation with a point-to-point precision of at least 5%.<br />
# Measure systematics of pi0/eta mass calibration as a function of detector position to a precision of at least 5 MeV.<br />
# Demonstrate agreement of photon reconstruction efficiency and resolution between data and simulation as a function of E, phi and theta to within 5%.<br />
<br />
= Action Items =<br />
<br />
# [[Short term CALWG Items]]<br />
# [[Long term items]]<br />
# [https://halldweb.jlab.org/wiki-private/index.php/2018_Work_Packages#Calorimetry Calorimeter work packages]<br />
# AI - BCAL Monitoring:<br />
## [https://halldweb.jlab.org/hydra/HydraRun.html Hydra Real-Time Dashboard]<br />
## [https://halldweb.jlab.org/hydra/HydraLog.html Hydra 24-hr Monitoring Logs]<br />
<br />
= Tentative Agenda =<br />
<br />
# Announcements<br />
# Past Meeting Minutes<br />
# Shutdown tasks<br />
## Review Action Items<br />
# Run Operations<br />
## FCAL<br />
## BCAL<br />
## CCAL<br />
# Calibration<br />
# Monitoring<br />
## BCAL (offline)<br />
## FCAL (offline) [[:file:Su-2022-03-16-FCAL-LED.pdf | FCAL-LED efficiencies and timing for 2021-08 PrimeX and 2021-11 SRC/CT]]<br />
## CCAL (offline)<br />
# Reconstruction<br />
# Simulations<br />
# Any other business<br />
<br />
= Minutes =<br />
''Attendees: Karthik, Susan, Mark, Tolga, Stjepan, Sean, Elton, Igal, Malte, Eugene, Jon, Zisis''<br />
<br />
# Announcements: none.<br />
# Past Meeting Minutes. We reviewed these; the FCAL voltage will be discussed at out next meeting when Matt is present. We might also get an update on the FCAL timing resolution that Rebecca is working on.<br />
# Shutdown tasks<br />
## CPP: Elton presented a comprehensive summary on the CPP installation progress. All is going well. All MWPCs have been tested and moved from EEL to the Hall and mounted on the forward carriage. Minor issues with the supplier of the cables required (soldering vs crimping of connectors). 6 cables exists that can be used to test each chamber; with 6 chambers, 36 50-ft cables are needed (horizontal chamber connectors are at the side, vertical ones at the top). The MWPCs will use a CDC FADC (corresponding to 1/4 of the CDC). Changes from GlueX standard configuration: i) 3/4 CDC operating (with BCAL to be used to veto charged particles in CPP and to look at photons at large angles BSL from NPP); ii) the tagger microscope is being moved down to 6 GeV, which has software and monitoring implications, as well as coherent peak implications. CPP requests that the FCAL stay the same to avoid introducing any additional changes into the CPP experiment. <br />
## Review Action Items: Zisis updated short, long and calorimeter work packages following our discussion two weeks ago.<br />
# Run Operations: no other updates<br />
# Calibration: Stjepan reported that he has started the pi0 gain calibrations for the first SRC batch (runs 90059-90200) based off the 2020 GlueX gains and the numbers look quite good. He will proceed to the next batches. We also discussed what to do for the PrimEx gain constants. Those looked very similar to the 2020 GlueX ones (a couple of channels had 2-3% deviation, all others within 1%) [[https://halldweb.jlab.org/doc-private/DocDB/ShowDocument?docid=5530]]. Karthik reported that the 2021 PrimEx numbest are consistent with the 2019 PrimEx ones. Mark mentioned that he finished the final timing calibration for the BCAL and will move next to the attenuation length and position calibrations; those could affect the gain calibrations. We decided to wait for Mark's numbers and then invite the PrimEx people to come to our CALWG to discuss thesis. It is possible that we might want to run a monitoring launch as a final check. <br />
# Monitoring<br />
## BCAL (offline): no report.<br />
## FCAL (offline): Susan gave a report on FCAL-LED efficiencies and timing for 2021-08 PrimeX and 2021-11 SRC/CT. Slide 2 is on PrimEx and slide 3 on SRC. Upper left plots: horizontal lines correspond to the various LED configurations (colours, voltages). Gaps in this plots may be related to entering the dark room to replace bases, according to Mark; the efficiency numbers form these should be good. This will be verified by looking at the archiver, which could have 3 variables related to this, according to Malte. Lower right plot should be used to check timing once the timing calibration (shifts) have been completed. On slide 2 upper right, there is a horizontal line at 25 on the y-axis; Susan will investigate further. On slide 3 there is a vertical line before run 90600; it might be noise, but we will wait for data monitoring.<br />
## CCAL (offline): no report.<br />
# Reconstruction: no report.<br />
# Simulations: no report.<br />
# Any other business: none.</div>Stjorehttps://halldweb1.jlab.org/wiki/index.php?title=January_5,_2022_Calorimeter&diff=109965January 5, 2022 Calorimeter2022-01-05T21:12:51Z<p>Stjore: /* Tentative Agenda */</p>
<hr />
<div><font color=red>Meeting Day/Time: every other WEDNESDAY at 11:00 a.m. JLab time</font>''<br><br />
<br />
=Connection instructions=<br />
<div class="toccolours mw-collapsible mw-collapsed"><br />
Use ZoomGov: https://jlab-org.zoomgov.com/j/1608552106?pwd=UE1nZFIzUUZHVjJEVGJXTGdUYTV3UT09. Our meeting ID number is '''160 855 2106'''. Click "Expand" for more details.<br />
<div class="mw-collapsible-content"><br />
* Meeting ID: 160 855 2106 Passcode: 944454<br />
* One tap mobile<br />
+16692545252,,1608552106# US (San Jose)<br />
+16468287666,,1608552106# US (New York)<br />
* Dial by your location<br />
+1 669 254 5252 US (San Jose)<br />
+1 646 828 7666 US (New York)<br />
+1 551 285 1373 US<br />
+1 669 216 1590 US (San Jose)<br />
833 568 8864 US Toll-free<br />
* Meeting ID: 160 855 2106<br />
* Find your local number: https://jlab-org.zoomgov.com/u/acAwPdiE89<br />
* Join by SIP 1608552106@sip.zoomgov.com<br />
* Join by H.323<br />
161.199.138.10 (US West)<br />
161.199.136.10 (US East)<br />
Meeting ID: 160 855 2106<br />
Passcode: 944454<br />
</div><br />
</div><br />
<br />
<br />
=Participant Direct Lines=<br />
<br />
* JLab Phone in CC L207 is 757-269-7084 (usual room)<br />
* JLab Phone: in CC F326 is 757-269-6460<br />
* Phone in the Regina Video-conference Suite is 306-585-4204<br />
* Athens Phone: in Christina's office is 011-30-210-727-6947<br />
<br />
= References =<br />
<br />
# FCAL [https://logbooks.jlab.org/book/hdfcal HDFCAL log book]<br />
# BCAL [https://logbooks.jlab.org/book/hdbcal HDBCAL log book]<br />
# CCAL [https://logbooks.jlab.org/book/hdccal HDCCAL log book]<br />
# Calibrations: [https://halldweb.jlab.org/wiki/index.php/2020_Data_Production 2020 Data Production]; [https://halldweb.jlab.org/wiki/index.php/RunPeriod-2019-11_Validation#Monitoring_Launch_Checks RunPeriod-2019-11 Validation]; [https://halldweb.jlab.org/wiki/index.php/Offline_Monitoring_Data_Validation Offline Monitoring Data Validation]<br />
# [https://halldweb.jlab.org/wiki-private/index.php/2020_Analysis_Task_Forces#Photon_Reconstruction_Systematics_Task_Force Photon Reconstruction Task Force]<br />
<br />
= Goals for Calorimetry Group =<br />
<br />
# Determine preliminary photon reconstruction efficiencies as a function of E, phi and theta in data and simulation with a point-to-point precision of at least 5%.<br />
# Measure systematics of pi0/eta mass calibration as a function of detector position to a precision of at least 5 MeV.<br />
# Demonstrate agreement of photon reconstruction efficiency and resolution between data and simulation as a function of E, phi and theta to within 5%.<br />
<br />
= Action Items =<br />
<br />
# [[Short term CALWG Items]]<br />
# [[Long term items]]<br />
# [https://halldweb.jlab.org/wiki-private/index.php/2018_Work_Packages#Calorimetry Calorimeter work packages]<br />
# AI - BCAL Monitoring:<br />
## [https://halldweb.jlab.org/hydra/HydraRun.html Hydra Real-Time Dashboard]<br />
## [https://halldweb.jlab.org/hydra/HydraLog.html Hydra 24-hr Monitoring Logs]<br />
<br />
= Tentative Agenda =<br />
<br />
# Announcements<br />
# Past Meeting Minutes<br />
# Run Operations<br />
## FCAL<br />
## BCAL<br />
## CCAL<br />
# Calibration<br />
## BCAL PrimEx runs (Stjepan): [https://halldweb.jlab.org/DocDB/0054/005411/001/Pi0_BCAL_Gain_Callibration_GlueX_v2.pdf]<br />
# Monitoring<br />
## BCAL LED Status of monitoring (Varun): SRC runs [https://halldweb.jlab.org/wiki/images/0/01/LED_Update_2022Jan05.pdf]<br />
## BCAL (offline)<br />
## FCAL (offline)<br />
# Reconstruction<br />
##Photon gun study (Churamani): [https://halldweb.jlab.org/DocDB/0053/005391/002/photon_efficiency_gun.pdf]<br />
# Simulations<br />
# Action Items<br />
# Any other business<br />
<br />
= Minutes =<br />
''Attendees:''</div>Stjore