Unnamed Project

Start: May 2, 2013
Finish: January 28, 2014
Report Date: April 16, 2013

Gantt Chart

WBS Name Work
     
1 25213005 Fabricate (FIU) Start Counter 1d
2 25213015 All_Manufacturing_Drawings_for_start_counter 1d
3 Procure_start_counter_support_frame_parts 1d
4 Assemble_start_counter_support_frame 1d
Week 19, 2013 Week 20, 2013 Week 21, 2013 Week 22, 2013 Week 23, 2013 Week 24, 2013 Week 25, 2013 Week 26, 2013 Week 27, 2013 Week 28, 2013 Week 29, 2013 Week 30, 2013 Week 31, 2013 Week 32, 2013 Week 33, 2013 Week 34, 2013 Week 35, 2013 Week 36, 2013 Week 37, 2013 Week 38, 2013 Week 39, 2013 Week 40, 2013 Week 41, 2013 Week 42, 2013 Week 43, 2013 Week 44, 2013 Week 45, 2013 Week 46, 2013 Week 47, 2013 Week 48, 2013 Week 49, 2013 Week 50, 2013 Week 51, 2013 Week 52, 2013 Week 1, 2014 Week 2, 2014 Week 3, 2014 Week 4, 2014 Week 5, 2014
3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4

Tasks

WBS Name Start Finish Work Complete Cost Assigned to
1 25213005 Fabricate (FIU) Start Counter Jul 1 Jan 28 1d 0%
2 25213015 All_Manufacturing_Drawings_for_start_counter May 3 Jun 14 1d 0%
3 Procure_start_counter_support_frame_parts Jun 19 Aug 13 1d 0%
4 Assemble_start_counter_support_frame Aug 22 Nov 1 1d 0%