Click the Last Maintenance date to update when the last maintenance was performed
Click the Task to EDIT the long description of this task
Click here to add a new item to the Hall D maintenance maintainer
TASK | Primary Contact | Secondary Contact | PERIOD (days) | NEXT MAINTENANCE | LAST MAINTENANCE |
Swap US BCAL Chiller | dallen@jlab.org | rmont@jlab.org | 350 | 09/02/25 | 09/17/24 |
1-Swap out the BCAL chillers with the "spare". 2- The purpose of this maintenance it to exercise each unit to help prevent it from failure from being idle. 3-When we change out the BCAL chillers or Watlow controllers we need to notify Hovanes which one (1, 2 or 3) is installed where (US or DS) so he can put the proper IP address in for remote signals. If just the Watlow controller is changed, give Hovanes the IP address off the controller. *Swapping and testing etc for JAN RUN* There are button controls on the epics css screen where we can swap the WATLOs ourselves and they seem to work -DCD 17-09-2024 |