Hall D Maintenance Status Long Description

Click the Last Maintenance date to update when the last maintenance was performed

Click the Task to EDIT the long description of this task

Click here to add a new item to the Hall D maintenance maintainer

TASK Primary Contact Secondary Contact PERIOD (days) NEXT MAINTENANCE LAST MAINTENANCE
Goni electronics boa keithb@jlab.org bunton@jlab.org 1275 02/25/27 08/30/23

Completely disassemble the goniometer and replace the electronics boards, regrease, assemble and test and re-install and align 9/10/2019- Perform dis-assembly and replace encoder boards , limit boards,lube bearings and lead screws.A broken wire was repaired on a stepper motor. Re-assemble components and test operation in survey lab. Install Goni in Tagger.Final survey to be done when diamonds arrive. 10/18/2019 Install diamonds in the positions as directed and install new V-wire. Survey was completed also.